  "evidence": "Original values and AMR transparent calculations, Nov 2026",
  "tables": [
    {
      "key": "iea-2035-high-case-gap-closure",
      "title": "Additional announced supply versus remaining demand requirement",
      "file": "iea-2035-high-case-gap-closure.csv",
      "rows": 3,
      "headers": [
        "Scenario",
        "Primary requirement (Mt)",
        "Base production (Mt)",
        "High-case production (Mt)",
        "Increment from high case (Mt)",
        "Base gap (Mt)",
        "Base gap closed (%)",
        "Remaining gap (Mt)",
        "Additional output relative to high case (%)"
      ],
      "sources": [
        "https://www.iea.org/data-and-statistics/charts/expected-mine-supply-from-existing-and-announced-projects-and-primary-supply-requirements-for-copper-by-scenario-2035"
      ],
      "method": "From IEA 2035 figure: high minus base; uplift divided by base gap; residual divided by high case supply. Conditional project cases, not forecasts of shortage."
    },
    {
      "key": "iea-existing-project-vintage",
      "title": "IEA base case supply by stage across vintages",
      "file": "iea-existing-project-vintage.csv",
      "rows": 2,
      "headers": [
        "Supply stage",
        "2025 historical (kt Cu)",
        "2030 base case (kt Cu)",
        "2040 base case (kt Cu)",
        "2030 to 2040 change (kt)",
        "2030 to 2040 relative change (%)"
      ],
      "sources": [
        "https://www.iea.org/files/19c60aa0-ee07-4a20-a138-33c967ac5008/GlobalCriticalMineralsOutlook2026.pdf#page=348"
      ],
      "method": "Annex table: 2040 base case minus 2030, divided by 2030. Stage totals are not subtractable as an apparent consumption balance."
    },
    {
      "key": "payne-capacity-capital-sensitivity",
      "title": "Illustrative capital multiplication from Payne Institute inputs",
      "file": "payne-capacity-capital-sensitivity.csv",
      "rows": 6,
      "headers": [
        "Capacity boundary",
        "Required capacity (Mt/y)",
        "Assumed capital intensity (2024 USD per annual tonne)",
        "AMR multiplication (2024 USD bn)"
      ],
      "sources": [
        "https://payneinstitute.mines.edu/the-investment-gap-in-copper-mining/"
      ],
      "method": "Payne Table 1 rounded source inputs. AMR multiplies millions of annual tonnes by USD per annual tonne, divided by 1,000. May differ slightly from source totals using unrounded inputs; not a project estimate or annual spend."
    },
    {
      "key": "payne-demand-case-capacity-cost",
      "title": "Payne scenario boundary and implied development capital",
      "file": "payne-demand-case-capacity-cost.csv",
      "rows": 5,
      "headers": [
        "Scenario or period",
        "Additional annual mine capacity (Mt/y)",
        "Common capital intensity (2024 USD per annual tonne)",
        "Implied development capital (2024 USD bn)"
      ],
      "sources": [
        "https://payneinstitute.mines.edu/the-investment-gap-in-copper-mining/"
      ],
      "method": "Table 1; source rounded capacities multiplied by fixed 26-project average intensity. Excludes sustaining, refining, exploration and finance costs. Baseline is 2026 onward except clearly labeled full period."
    }
  ]
}