  "evidence": "Original values and AMR transparent calculations, Nov 2026",
  "tables": [
    {
      "key": "chile-grade-and-output-paired-history",
      "title": "Chile national grade and copper output, 2000–2025",
      "file": "chile-grade-and-output-paired-history.csv",
      "rows": 26,
      "headers": [
        "Year",
        "Ore-weighted grade (%)",
        "Mine output (kt Cu)",
        "Grade index (2000=100)",
        "Mine output index (2000=100)",
        "Illustrative ore tonnes per recovered tonne at 85%",
        "Workbook cells"
      ],
      "sources": [
        "https://www.cochilco.cl/web/download/1036/2026/16850/base-de-datos-anuario-de-estadisticas-cochilco"
      ],
      "method": "Cochilco Tables 2.1 and 2.4; each index is current divided by 2000 times 100. Hypothetical ore mass: 100 divided by grade percent and 0.85. Ore and production scopes are not a closed mine mass balance."
    },
    {
      "key": "chile-copper-production-stages",
      "title": "Chile annual copper production across reported stages",
      "file": "chile-copper-production-stages.csv",
      "rows": 26,
      "headers": [
        "Year",
        "Mine (kt)",
        "Smelter (kt)",
        "Refined (kt)",
        "SX-EW cathodes (kt)",
        "Electrorefined cathodes (kt)",
        "Fire refined (kt)",
        "Workbook cells"
      ],
      "sources": [
        "https://www.cochilco.cl/web/download/1036/2026/16850/base-de-datos-anuario-de-estadisticas-cochilco"
      ],
      "method": "Cochilco Table 2.1 rows 8–13. Refined subcategories are components rounded independently; stages cannot be summed or used to calculate plant recovery."
    },
    {
      "key": "chile-grade-cost-productivity-context",
      "title": "Published national grade and selected large-miner cost and productivity context",
      "file": "chile-grade-cost-productivity-context.csv",
      "rows": 21,
      "headers": [
        "Year",
        "Chile ore-weighted grade (%)",
        "GMP-10 plus Codelco real unit cost index (2005=100)",
        "Codelco own-workforce productivity index (2005=100)",
        "Workbook cells"
      ],
      "sources": [
        "https://www.cochilco.cl/web/download/1036/2026/16850/base-de-datos-anuario-de-estadisticas-cochilco"
      ],
      "method": "Cochilco Tables 2.4, 2.5, 2.6. Grade is national; cost series covers defined large mining groups and the productivity index covers Codelco own employees, not a matched national causal sample."
    },
    {
      "key": "recovery-sensitivity-at-reported-grades",
      "title": "Illustrative recovery sensitivity at two reported national grades",
      "file": "recovery-sensitivity-at-reported-grades.csv",
      "rows": 6,
      "headers": [
        "Grade year",
        "Head grade (%)",
        "Assumed recovery (%)",
        "Recovered kg per tonne ore",
        "Ore tonnes per recovered tonne Cu"
      ],
      "sources": [
        "https://www.cochilco.cl/web/download/1036/2026/16850/base-de-datos-anuario-de-estadisticas-cochilco"
      ],
      "method": "Source grade from Table 2.4. Recovery assumptions chosen for sensitivity, not observed. Recovered mass is ore grade × assumed recovery; no losses outside assumed recovery."
    },
    {
      "key": "chile-electricity-intensity-dual-denominators",
      "title": "Chile electricity intensity per copper tonne versus per feed tonne, 2005–2024",
      "file": "chile-electricity-intensity-dual-denominators.csv",
      "rows": 100,
      "headers": [
        "Year",
        "Process",
        "Copper denominator",
        "MJ per t Cu",
        "Material denominator",
        "MJ per t material",
        "Workbook cells"
      ],
      "sources": [
        "https://www.cochilco.cl/web/download/1036/2026/16850/base-de-datos-anuario-de-estadisticas-cochilco"
      ],
      "method": "Cochilco Tables 6.8 and 6.9, matched process labels and complete years. The 2025 edition expressly says 2025 energy figures were not available at closing; retain 2005–24 window. Denominators differ by stage."
    }
  ]
}