Electricity Grid Copper and Aluminium Demand Statistics

Updated

Quick Answer

Electricity networks used 4.544 million metric tonnes of refined copper in 2025, according to the IEA’s historical estimate. That was 16.36% of total refined copper demand and 56.78% of clean-energy copper demand, calculated by AMR. The IEA’s 2040 scenarios span 6.631 to 7.181 million tonnes of network copper. A separate IEA study published in 2021 also gives copper and aluminium by grid segment. (IEA Global Critical Minerals Outlook 2026, Annex p. 347, accessed, Nov 2026).

Electricity networks and EVs contributed different increments to copper growth. From 2021 to 2025, IEA electricity-network copper demand rose 355 kt and EV copper demand rose 530 kt. These represented 12.57% and 18.76% of the 2,825 kt net rise in refined copper demand. IEA 2026 Annex rounded historical series; direct use of scrap excluded. (IEA Critical Minerals Outlook 2026, p. 347.) Cite this finding.

On this page
  1. Quick Answer
  2. Key Takeaways
  3. Source comparison
  4. What share of world copper demand goes into electricity networks?
  5. How much copper could electricity networks use in 2040 and 2050?
  6. How much copper and aluminium go into transmission and distribution?
  7. Which grid statistics can be compared directly?
  8. How does grid copper demand compare with EVs, solar and other uses?
  9. Which grid segment is responsible for the largest increase in metal demand?
  10. How long does it take to procure grid equipment, and what materials matter?
  11. How large is the grid investment and connection challenge?
  12. Why is grid expansion not just a metal-per-kilometre calculation?
  13. Methodology and sources

Key Takeaways

How much of modeled grid copper growth comes from distribution and transformers?

Distribution and transformers together add 1.66 Mt copper in the IEA’s 2020 to 2040 Stated Policies grid comparison. That is 62.88% of the model’s copper increment across the three grid components. (IEA, grid copper and aluminium demand components, 2020 to 2040 STEPS, Nov 2026).

Calculated comparisonResultCalculation
Distribution and transformer increment1.66 Mt copperA + B
Combined share of the three increments62.88%(A + B) ÷ (A + B + C) × 100
Combined increment per transmission tonne1.69 times(A + B) ÷ C

This decomposition allocates the increment to three reported components within the same scenario and publication vintage. Combining distribution and transformers is an AMR grouping. The IEA 2026 electricity networks series is a different vintage and does not update these component shares.

How to use this comparison

To support a statement about transmission infrastructure, cite the transmission increment and its share of grid copper growth. To size total grid metal demand, include distribution and transformers with their own assumptions. Related evidence on Copper Supply and Demand Statistics: Production, Recycling and Projected Gaps.

Reproduce the numbers

Each letter in the calculation maps to a source value below. Calculate from the displayed source values and round the result only at the end. The download records the source file, row, field and formula.

InputWhat is measuredSource valueExact source row and field
ACopper distribution increment1.42STEPS · Increase (Mt)
BCopper transformer increment0.24STEPS · Increase (Mt)
CCopper transmission increment0.98STEPS · Increase (Mt)

Download the calculation and source rows (CSV)

Cite this comparison

Distribution and transformers together add 1.66 Mt copper in the IEA’s 2020 to 2040 Stated Policies grid comparison. That is 62.88% of the model’s copper increment across the three grid components. American Mineral Registry calculation from IEA, grid copper and aluminium demand components, 2020 to 2040 STEPS. 2020 to 2040 Stated Policies Scenario in the IEA 2021 grid decomposition. https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics#amr-reader-analysis

HTML attribution

<a href="https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics#amr-reader-analysis">How much of modeled grid copper growth comes from distribution and transformers?</a>

What share of world copper demand goes into electricity networks?

The 2026 IEA data give 4,544 kt for electricity networks, 8,003 kt for all clean-energy uses, and 27,775 kt for total refined copper demand in 2025. A grid-focused story can use the first quantity on its own. To describe its market share, use the world total. To describe its role in clean energy, use the clean-energy subtotal. The model’s refined copper demand series excludes direct use of scrap. (IEA 2026 Copper demand, Annex p. 347, accessed, Nov 2026).

IEA global refined copper demand in 2021 and 2025, kilotonnes. Networks 4,189 and 4,544. Electric vehicles 264 and 794. Solar PV 707 and 1,970.
Figure 1: Network demand rose in tonnes while electric vehicles and solar PV gained share of the clean-energy total. Source: IEA Global Critical Minerals Outlook 2026, Annex p. 347, Nov 2026. Chart drawn by American Mineral Registry from the source figures, checked 25 Nov 2026.
View chart data

IEA 2026 estimates, kilotonnes of refined copper demand. Selected uses within clean energy.

Grid copper grew alongside faster-growing end uses
End use2021 (kt Cu)2025 (kt Cu)
Networks41894544
Electric vehicles264794
Solar PV7071970

Values and definitions are also readable in HTML. Source precision and scope apply.

IEA Global Critical Minerals Outlook 2026, Annex p. 347, Nov 2026 Original primary evidence

Download this figure (SVG)

IEA 2026 historical change
Use or aggregate2021 (kt Cu)2025 (kt Cu)Absolute change (kt Cu)Relative change (%)
Networks418945443558.47
Electric vehicles264794530200.76
Solar PV70719701263178.64
Clean energy subtotal56548003234941.55
Total copper demand2495027775282511.32

IEA Annex, p. 347 · Download matching CSV

Growth in the clean-energy copper denominator was 2,349 kt between the two estimates. Networks added 355 kt, which is 15.11% of that increase. Solar PV added 1,263 kt, and electric vehicles added 530 kt. A falling network share is consistent with rising absolute grid demand because the other parts of the subtotal grew faster. The three named rows are components of the clean-energy total. The total also includes other clean-energy uses. (IEA 2026 Annex p. 347, historical columns, accessed, Nov 2026).

How much copper could electricity networks use in 2040 and 2050?

All three 2040 cases exceed the IEA’s 2025 network estimate. The 2040 Stated Policies result is 6,631 kt, about 45.93% above the 2025 estimate. It represents 18.95% of total refined copper in that scenario. The High Demand result is 7,181 kt, or 20.10% of all refined copper demand in its case. These comparisons keep the same end-use label and measure across the 2026 source. (IEA 2026 Annex p. 347, demand scenarios, accessed, Nov 2026).

IEA 2040 electricity network refined copper demand in kilotonnes. Current Policies 6,693. Stated Policies 6,631. High Demand 7,181.
Figure 2: The three values refer to the same year and the same end-use definition. Source: IEA 2026 Copper demand scenario table, Nov 2026. Chart drawn by American Mineral Registry from the source figures, checked 25 Nov 2026.
View chart data

IEA 2026 model. Kilotonnes of refined copper demand in electricity networks.

The 2040 grid result depends on the demand case
Scenario2040 grid copper demand (kt)
Current Policies (CPS)6693
Stated Policies (STEPS)6631
High Demand (HDS)7181

Values and definitions are also readable in HTML. Source precision and scope apply.

IEA 2026 Copper demand scenario table, Nov 2026 Original primary evidence

Download this figure (SVG)

IEA 2026 copper demand by grid scenario
IEA evidence type or scenarioYearElectricity network demand (kt Cu)Clean-energy demand (kt Cu)Total demand (kt Cu)Network share of clean-energy Cu (%)Network share of all Cu (%)
Historical estimate2021418956542495074.0916.79
Historical estimate2025454480032777556.7816.36
Current Policies (CPS)20305637102323079255.0918.31
Current Policies (CPS)20406693118223358056.6119.93
Current Policies (CPS)20506430121743588852.8217.92
Stated Policies (STEPS)20305713107253137053.2718.21
Stated Policies (STEPS)20406631130733498450.7218.95
Stated Policies (STEPS)20506316135593757246.5816.81
High Demand (HDS)20306002123023196748.7918.78
High Demand (HDS)20407181156683571945.8320.10
High Demand (HDS)20506815165723806641.1217.90

IEA Annex, p. 347 · Download matching CSV

The scenario ordering varies by measure. In 2040, Current Policies has 6,693 kt of network demand, 62 kt above Stated Policies, while its all-use total of 33,580 kt is below Stated Policies’ 34,984 kt. Looking only at total copper would therefore give the wrong order for those two grid values. Also, all three 2050 grid results sit below their own 2040 values even as total copper demand increases in those cases. Both observations describe the IEA model outputs at the reported milestones. (IEA 2026 Annex p. 347, scenario rows, accessed, Nov 2026).

How much copper and aluminium go into transmission and distribution?

The IEA’s 2021 study gives five chart components. In the 2040 Sustainable Development Scenario, copper totals 10.01 Mt from 3.25 Mt transmission, 5.91 Mt distribution, and 0.85 Mt transformers. Aluminium totals 16.32 Mt from 6.07 Mt transmission and 10.25 Mt distribution. Those figures include grid expansion and replacement under the published chart definition. (IEA Sustainable Development Scenario grid chart, May 2021).

IEA 2021 Sustainable Development Scenario for 2040. Copper transmission 3.25 and distribution 5.91 million tonnes. Aluminium transmission 6.07 and distribution 10.25 million tonnes.
Figure 3: Distribution is larger than transmission for both materials in the source chart. The source separately gives a copper transformer component. Source: IEA 2021 Sustainable Development Scenario grid chart, May 2021. Chart drawn by American Mineral Registry from the source figures, checked 25 Nov 2026.
View chart data

IEA 2021 Sustainable Development Scenario, million metric tonnes. Transformers are a separate copper row.

Distribution is the larger 2040 grid line component
MetalTransmission (Mt)Distribution (Mt)
Copper3.255.91
Aluminium6.0710.25

Values and definitions are also readable in HTML. Source precision and scope apply.

IEA 2021 Sustainable Development Scenario grid chart, May 2021 Original primary evidence

Download this figure (SVG)

IEA 2021 grid metal components
2021 outlook caseYearCu transmission (Mt)Cu distribution (Mt)Cu transformers (Mt)Al transmission (Mt)Al distribution (Mt)
STEPS20201.842.740.394.154.96
STEPS20302.473.270.494.955.85
STEPS20402.824.160.635.517.36
SDS20201.842.740.394.154.96
SDS20302.703.860.755.266.81
SDS20403.255.910.856.0710.25

IEA source · IEA source · Download matching CSV

Distribution represents 59.04% of the copper total and 62.81% of the aluminium total in that case. The copper denominator includes transformers. The aluminium panel covers the two published line components. AMR does not infer an aluminium transformer quantity from that chart.

IEA 2021 grid metal totals
2021 outlook caseYearCopper (Mt)Aluminium (Mt)Combined metal mass (Mt)Copper distribution share (%)Aluminium distribution share (%)
STEPS20204.979.1114.0855.1354.45
STEPS20306.2310.8017.0352.4954.17
STEPS20407.6112.8720.4854.6657.19
SDS20204.979.1114.0855.1354.45
SDS20307.3112.0719.3852.8056.42
SDS204010.0116.3226.3359.0462.81

IEA source · IEA source · Download matching CSV

For 2040, the 2021 study’s Stated Policies components sum to 7.61 Mt copper and 12.87 Mt aluminium, or 20.48 Mt combined. The Sustainable Development components sum to 26.33 Mt combined, a gap of 5.85 Mt between the cases. Combined tonnes express demand by mass. A pricing or conductivity comparison needs its own matched dimensions. (IEA 2021 Stated Policies grid chart, May 2021). (IEA 2021 Sustainable Development grid chart, May 2021).

Where can substitution affect demand?

The IEA’s 2021 discussion identifies weight as one reason aluminium is commonly used above ground, with copper common in underground and subsea uses where other performance properties matter. Its illustrative case puts more aluminium into underground and subsea cables. In that modeled case, 2040 copper demand falls by 3.6 Mt and aluminium demand rises by 5.8 Mt. Those are scenario differences from the producer’s analysis. Cable performance and the feasibility of substitution depend on the design and environment. (IEA grid materials and technology choices, May 2021).

Which grid statistics can be compared directly?

Use the 2026 refined-copper dataset to compare grid copper against other end uses, historical points or the three scenarios in that edition. Use the 2021 grid component dataset to compare copper and aluminium by segment and to reproduce the 2021 study’s scenario totals for 2040. The two editions have different stated boundaries and forecasting contexts. A revision comparison would need explicit evidence that those inputs are matched. Both sets are available for different research questions.

Grid model boundaries
SourceEvidence years and casesMaterialsDemand boundaryMethod note
IEA 2026 copper annex2021 and 2025 history; three future casesRefined copper onlyElectricity networks, with separate clean-energy and all-uses denominatorsExcludes direct use of scrap in the refined copper series
IEA 2021 grid materials charts2020 benchmark; 2030 and 2040 STEPS and SDSCopper and aluminium componentsTransmission, distribution and copper transformer seriesIncludes expansion and replacement. Distinct model vintage

IEA Annex, p. 347 · IEA source · Download matching CSV

How does grid copper demand compare with EVs, solar and other uses?

The 2026 IEA copper demand table is particularly valuable because it gives electricity networks, electric vehicles, solar PV, other clean energy and non-clean-energy uses within the same refined-copper accounting boundary. It allows analysis of both the largest end-use level and the incremental change. From 2021 to 2025 electricity networks rose from 4,189 to 4,544 kt, a net gain of 355 kt. Electric vehicles rose from 264 to 794 kt, a gain of 530 kt. Solar PV rose from 707 to 1,970 kt. The networks category remained much larger than EVs in 2025, but EVs accounted for a larger increase over those four years. Ranking sectors by current tonnes answers a different question from ranking them by new demand.

What drove historical copper demand growth?. Change in refined copper demand, kt Cu, from 2021 to 2025.
Figure 4: Change in refined copper demand, kt Cu, from 2021 to 2025. Sources: IEA Critical Minerals Outlook 2026, p. 347. See the full supporting table below.
View chart data

Change in refined copper demand, kt Cu, from 2021 to 2025.

What drove historical copper demand growth?
End-use categoryChange (kt Cu)
Electricity networks355
Electric vehicles530
Solar PV1263
Other clean energy202
Other uses (non-clean)476

Figures retain the source units and definitions.

IEA Critical Minerals Outlook 2026, p. 347

Download chart data · Download chart SVG

2021–25 copper demand change by end-use row
Demand row2021 (kt)2025 (kt)Change (kt)Growth (%)Share of total net growth (%)
Clean energy56548003234941.5583.15
Electricity networks418945443558.4712.57
Electric vehicles264794530200.7618.76
Solar PV70719701263178.6444.71
Other49369520240.977.15
Other uses19296197724762.4716.85
Total demand2495027775282511.32100.00

IEA Critical Minerals Outlook 2026, p. 347 · Download matching CSV

AMR difference of original rows; contribution denominator is total demand change. Parent totals overlap child rows; do not sum all rows.

Total refined copper demand in the table increased by 2,825 kt from 2021 to 2025. The contribution column divides each row’s change by that total change. The electricity network, EV, PV and other clean rows are children of the “All clean energy” parent. Combining every row's contribution would double count the parent and the children. Readers comparing industries should use one level of that hierarchy; the separate rounding residual prevents precision beyond the numbers displayed in the source.

Scroll the full table to compare columns and rows. The complete data are also available as a CSV.

IEA 2026 detailed copper demand by use, scenario and year
CaseYearNetworks (kt)Electric vehicles (kt)Solar PV (kt)Other clean energy (kt)All clean energy (kt)Other uses (kt)Total (kt)Clean parent minus components (kt)Total minus parents (kt)Networks share of total (%)EV share of total (%)
Historical20214189264707493565419296249501016.791.06
Historical202545447941970695800319772277750016.362.86
CPS20305637162320449271023220560307921018.315.27
CPS204066932359175510151182221757335800119.937.03
CPS205064302391209912531217423714358881017.926.66
STEPS20305713176322221066107252060531370-394018.215.62
STEPS204066313046221911771307321911349840018.958.71
STEPS205063163476230014661355924014375721-116.819.25
HDS203060022017280314801230219665319670018.786.31
HDS20407181414326261719156682005135719-1020.1011.60
HDS205068154750275822491657221495380660-117.9012.48

IEA Critical Minerals Outlook 2026, p. 347 · Download matching CSV

Original Annex demand rows. Parent/component differences reflect published rounding. Refined copper demand excludes direct scrap use. Cases are not observations.

The historical years, Current Policies Scenario, Stated Policies Scenario and High Demand Scenario are explicitly distinguished. The scenarios are alternative assumptions; their difference is not a confidence interval or historical volatility measure. The IEA demand boundary is refined copper and excludes direct use of scrap. In addition, the EV line includes both batteries and motors. That makes it unsuitable for direct comparison with a source estimating copper in battery cells alone. IEA Global Critical Minerals Outlook 2026, Annex demand table.

Which grid segment is responsible for the largest increase in metal demand?

The 2021 IEA outlook supplies the detailed grid component split for both metals that is not given by the 2026 copper end-use table. In the earlier Sustainable Development Scenario, copper distribution increases from 2.74 Mt in 2020 to 5.91 Mt in 2040; transmission increases from 1.84 to 3.25 Mt and transformers from 0.39 to 0.85 Mt. The distribution increment of 3.17 Mt is therefore about 62.90% of the total incremental grid copper mass in that scenario. Aluminium distribution rises from 4.96 to 10.25 Mt, an increase of 5.29 Mt.

2020–40 grid metal increase by component in the 2021 outlook
ScenarioComponent2020 (Mt)2040 (Mt)Increase (Mt)Growth (%)Share of same-metal increase (%)
STEPSCopper transmission1.842.820.9853.2637.12
STEPSCopper distribution2.744.161.4251.8253.79
STEPSCopper transformers0.390.630.2461.549.09
STEPSAluminium transmission4.155.511.3632.7736.17
STEPSAluminium distribution4.967.362.4048.3963.83
SDSCopper transmission1.843.251.4176.6327.98
SDSCopper distribution2.745.913.17115.6962.90
SDSCopper transformers0.390.850.46117.959.13
SDSAluminium transmission4.156.071.9246.2726.63
SDSAluminium distribution4.9610.255.29106.6573.37

IEA 2021 clean energy mineral requirements · Download matching CSV

Original IEA 2021 grid chart. Sum increments separately for Cu and Al per case. Historical-vintage scenarios, not current projections or all-use copper demand.

The component-share denominator is the total increase of that particular metal, not the total increase of copper and aluminium added together. The 2021 IEA scenarios reflect that study vintage and its model boundary. They are retained as a valuable segment-level dataset, not asserted to be a prediction from the current 2026 outlook. Subtracting the 2026 historical network figure from the 2021 scenario's component total would mix vintages and definitions. IEA 2021 mineral requirements for clean energy transitions.

How long does it take to procure grid equipment, and what materials matter?

A grid infrastructure project can have enough copper at the metal-market level yet face difficulty securing a manufactured cable or transformer. In its 2025 report on transmission grids, the IEA surveyed leading industry players and reported cable procurement periods of two to three years, up to four years for large power transformers and more than five years for direct-current cables. It also found cable prices nearly doubled compared with 2019 and transformer prices rose by about 75%. These are industry-survey observations and reported typical or upper-range periods, not universal quotes or forecasts for every manufacturer. Individual cable orders vary greatly by their voltage, capacity, route and engineering specification. IEA Building the Future Transmission Grid, executive summary.

Component procurement, mass and cost evidence
ComponentMeasureIEA reported quantityUnit or denominatorScope
CablesProcurement time2–3YearsSurvey of leading industry players, report published 2025
Large power transformersProcurement timeUp to 4YearsSurvey of leading industry players, report published 2025
Direct current cablesProcurement timeOver 5YearsSpecialised component availability
CablesPrice change since 2019Nearly doubledRelative to 2019Survey; project complexity varies
Power transformersPrice change since 2019About 75Percent increaseSurvey; project complexity varies
High-voltage overhead lineAluminium compositionAbout 18Percent massIncludes steel poles in denominator
Copper cableCopper compositionAbout 60Percent massRemaining weight comprises insulation
Aluminium cableAluminium compositionUp to 80Percent massNot interchangeable with overhead line denominator
Large power transformerGOES coreOver 20Percent of total costCost share, not weight
Large power transformerMaterialsOver 50Percent of total costCan exceed 50%; includes other materials

IEA Transmission Grid 2025, p. 8 · IEA Transmission Grid 2025, p. 24 · Download matching CSV

IEA Building the Future Transmission Grid, 2025, executive summary and materials discussion; supplier-survey descriptions and engineering examples, not universal specifications.

The same report distinguishes the material composition of equipment from cost shares. It illustrates a high-voltage overhead line with aluminium approximately 18% of its composition when the steel poles are included. Copper cable is about 60% copper by weight in the example, whereas aluminium cable can be up to 80% aluminium. A transformer core using grain-oriented electrical steel represents more than 20% of transformer cost in the IEA discussion; all materials together can exceed 50% of cost. These different denominators must not be used interchangeably. For example, the overhead-line aluminium share does not equal the share of aluminium in an individual conductor. IEA materials discussion.

How large is the grid investment and connection challenge?

The transmission report provides useful context beyond equipment procurement. Global transmission investment reached USD 140 billion in 2023, up 10% during that year. Under the report's current-policy settings, annual spending would need to exceed USD 200 billion by the mid-2030s; in emissions-goal scenarios it would reach USD 250–300 billion. The IEA also tracked 1,650 GW in advanced-stage wind and solar projects awaiting connections in 2024. This illustrates the difference between projected generation capacity and the infrastructure needed to make it useful.

Grid investment, connection queue and workforce benchmarks
MeasureYear or horizonEvidence typeQuantityUnitQualification
Global power transmission investment2023Observed140USD billion10% growth in 2023
Annual global power transmission investmentMid-2030sToday’s policy settingsOver 200USD billion per yearIEA requirement scenario
Annual global power transmission investmentMid-2030sEmissions goals achieved in full250–300USD billion per yearIEA requirement scenarios
Solar and wind projects awaiting grid connection2024IEA tracking of advanced projects1650GWProject capacity, not copper demand
Employment in construction, maintenance and operation of gridsReport 2025IEA estimateAround 8Million peopleWorldwide grid workforce
Additional global grid workforce2030Today’s policy settings1.5Million peopleIncrease from report-period workforce

IEA Transmission Grid 2025, p. 7 · IEA Transmission Grid 2025, p. 8 · Download matching CSV

IEA Building the Future Transmission Grid, 2025, executive summary pp. 7–8. Financial investment, generation project capacity and labour are separate quantities; ranges and qualifiers retained.

The workforce constraint is another separate measure: the IEA estimates around eight million workers worldwide in grid construction, maintenance and operation, with another 1.5 million required by 2030 under its then-current policy settings. The monetary values in the table cover transmission, whereas workforce estimates cover grids more broadly and the queue is measured in generation capacity. They cannot be added or converted to copper tonnes without independent project bills of materials and assumptions. IEA report, pp. 7–8.

Why is grid expansion not just a metal-per-kilometre calculation?

Copper and aluminium have different electrical conductivity, mass, mechanical properties and installation constraints. Aluminium's conductivity-to-weight advantages often support overhead lines; underground and subsea applications may use copper or aluminium depending on the design. A kilometre of distribution cable is not directly comparable to a kilometre of high-voltage transmission line, and transformer requirements depend on capacity and voltage conversion as well as physical line length. To derive defensible metal requirements for a real project, use the actual equipment bill of materials, quantity and conductor or circuit specifications; national scenario totals are not a substitute.

Sector-level raw material demand, project procurement and total investment are three separate measurements. Metal tonnes can be used to estimate exposure to physical commodity availability; manufacturer survey wait times address supply-chain bottlenecks; project investment includes equipment, installation, permitting and other costs. Multiplying a total annual copper demand figure by a spot commodity price cannot yield the total cost of the corresponding grid build. Likewise, growth in EV or solar copper demand does not directly specify the network upgrades required to connect them. The end-use dataset and component-specific comparisons together allow each claim to be traced to its own denominator. See copper forecast boundaries for why electricity-network demand should not be substituted directly into an all-use primary mine supply deficit.

Methodology and sources

The expanded comparisons retain original source periods and row-level source references. Formulas, scope and precision are documented immediately beside each table, in the downloadable methods and source-cell ledger. Rounded primary values are not treated as exact unrounded observations.

AMR extracted the Electricity networks, Clean energy and Total demand rows from the 2026 copper demand table on Annex page 347. The chart on historical end uses also uses the Electric vehicles and Solar PV rows. Shares use the independently published parent totals. For the 2021 scenarios AMR sums the published transmission, distribution and copper transformer values. The calculations use the underlying CSV precision. The producer text uses rounded narrative totals. AMR records the evidence stage and scenario in each row and preserves the original named source for both editions.

Glossary

  • Electricity networks: The IEA copper demand row for the electricity network end use.
  • Transmission: The bulk-transfer part of the network, listed separately in the 2021 grid material charts.
  • Distribution: The network serving local customers, with its own metal demand series in those charts.
  • Transformer: Equipment that changes voltage levels. The IEA’s 2021 chart reports a copper transformer component.
  • Refined copper demand: Copper demand under the IEA 2026 model’s stated definition, excluding direct use of scrap.
  • STEPS and SDS: The Stated Policies Scenario and Sustainable Development Scenario in the 2021 source.

Sources

Cite a specific finding

Copy the exact comparison with its period, scope and original evidence.

Electricity networks used 16.36% of refined copper in the IEA’s 2025 estimates

AMR divides the IEA’s 4,544 kt of electricity network copper demand by 27,775 kt of world refined demand. Networks account for 16.36% of the total and 56.78% of clean-energy copper demand.

IEA 2026 Annex p. 347 historical estimate. The refined copper series excludes direct use of scrap.

American Mineral Registry. AMR divides the IEA’s 4,544 kt of electricity network copper demand by 27,775 kt of world refined demand. Networks account for 16.36% of the total and 56.78% of clean-energy copper demand. IEA 2026 Annex p. 347 historical estimate. The refined copper series excludes direct use of scrap. https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics#2025-grid-copper-demand-share Original evidence: https://www.iea.org/files/19c60aa0-ee07-4a20-a138-33c967ac5008/GlobalCriticalMineralsOutlook2026.pdf#page=347
HTML attribution<a href="https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics#2025-grid-copper-demand-share">American Mineral Registry</a>. AMR divides the IEA’s 4,544 kt of electricity network copper demand by 27,775 kt of world refined demand. Networks account for 16.36% of the total and 56.78% of clean-energy copper demand. IEA 2026 Annex p. 347 historical estimate. The refined copper series excludes direct use of scrap. Original evidence: <a href="https://www.iea.org/files/19c60aa0-ee07-4a20-a138-33c967ac5008/GlobalCriticalMineralsOutlook2026.pdf#page=347">IEA Annex, p. 347</a>.

Supporting table · Permanent finding link · Matching CSV · IEA Annex, p. 347

The 2040 grid copper scenarios span 6,631 to 7,181 kt

The IEA’s 2040 grid copper figures are 6,631 kt under Stated Policies, 6,693 under Current Policies and 7,181 under High Demand. The spread is 550 kt.

All three values come from the same IEA 2026 electricity networks row.

American Mineral Registry. The IEA’s 2040 grid copper figures are 6,631 kt under Stated Policies, 6,693 under Current Policies and 7,181 under High Demand. The spread is 550 kt. All three values come from the same IEA 2026 electricity networks row. https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics#2040-grid-copper-scenario-spread Original evidence: https://www.iea.org/files/19c60aa0-ee07-4a20-a138-33c967ac5008/GlobalCriticalMineralsOutlook2026.pdf#page=347
HTML attribution<a href="https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics#2040-grid-copper-scenario-spread">American Mineral Registry</a>. The IEA’s 2040 grid copper figures are 6,631 kt under Stated Policies, 6,693 under Current Policies and 7,181 under High Demand. The spread is 550 kt. All three values come from the same IEA 2026 electricity networks row. Original evidence: <a href="https://www.iea.org/files/19c60aa0-ee07-4a20-a138-33c967ac5008/GlobalCriticalMineralsOutlook2026.pdf#page=347">IEA Annex, p. 347</a>.

Supporting table · Permanent finding link · Matching CSV · IEA Annex, p. 347

Distribution used the larger share of both metals in the 2040 SDS

AMR calculates that distribution accounted for 5.91 of 10.01 Mt of copper demand and 10.25 of 16.32 Mt of aluminium demand in the older IEA 2040 Sustainable Development Scenario.

Uses the IEA’s 2021 grid chart components. The copper denominator includes a 0.85 Mt transformer component.

American Mineral Registry. AMR calculates that distribution accounted for 5.91 of 10.01 Mt of copper demand and 10.25 of 16.32 Mt of aluminium demand in the older IEA 2040 Sustainable Development Scenario. Uses the IEA’s 2021 grid chart components. The copper denominator includes a 0.85 Mt transformer component. https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics#grid-copper-aluminium-distribution-share Original evidence: https://www.iea.org/data-and-statistics/charts/demand-for-copper-and-aluminium-for-electricity-grids-in-the-sustainable-development-scenario-2020-2040
HTML attribution<a href="https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics#grid-copper-aluminium-distribution-share">American Mineral Registry</a>. AMR calculates that distribution accounted for 5.91 of 10.01 Mt of copper demand and 10.25 of 16.32 Mt of aluminium demand in the older IEA 2040 Sustainable Development Scenario. Uses the IEA’s 2021 grid chart components. The copper denominator includes a 0.85 Mt transformer component. Original evidence: <a href="https://www.iea.org/data-and-statistics/charts/demand-for-copper-and-aluminium-for-electricity-grids-in-the-sustainable-development-scenario-2020-2040">IEA source</a>.

Supporting table · Permanent finding link · Matching CSV · IEA source

Electricity networks and EVs contributed different increments to copper growth

From 2021 to 2025, IEA electricity-network copper demand rose 355 kt and EV copper demand rose 530 kt. These represented 12.57% and 18.76% of the 2,825 kt net rise in refined copper demand.

IEA 2026 Annex rounded historical series; direct use of scrap excluded.

American Mineral Registry. From 2021 to 2025, IEA electricity-network copper demand rose 355 kt and EV copper demand rose 530 kt. These represented 12.57% and 18.76% of the 2,825 kt net rise in refined copper demand. IEA 2026 Annex rounded historical series; direct use of scrap excluded. https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics#grid-versus-ev-demand-growth Original evidence: https://www.iea.org/files/19c60aa0-ee07-4a20-a138-33c967ac5008/GlobalCriticalMineralsOutlook2026.pdf#page=347
HTML attribution<a href="https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics#grid-versus-ev-demand-growth">American Mineral Registry</a>. From 2021 to 2025, IEA electricity-network copper demand rose 355 kt and EV copper demand rose 530 kt. These represented 12.57% and 18.76% of the 2,825 kt net rise in refined copper demand. IEA 2026 Annex rounded historical series; direct use of scrap excluded. Original evidence: <a href="https://www.iea.org/files/19c60aa0-ee07-4a20-a138-33c967ac5008/GlobalCriticalMineralsOutlook2026.pdf#page=347">IEA Critical Minerals Outlook 2026, p. 347</a>.

Supporting table · Permanent finding link · Matching CSV · IEA Critical Minerals Outlook 2026, p. 347

Grid equipment availability can delay construction independently of metal supply

The IEA’s 2025 transmission report found cable procurement generally took two to three years, large power transformers up to four years, and direct-current cables more than five years.

Survey of leading industry participants; not universal durations or a mine lead-time statistic.

American Mineral Registry. The IEA’s 2025 transmission report found cable procurement generally took two to three years, large power transformers up to four years, and direct-current cables more than five years. Survey of leading industry participants; not universal durations or a mine lead-time statistic. https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics#transmission-cable-transformer-waiting-times Original evidence: https://www.iea.org/files/744ff0bb-905a-4f9f-83e3-2d04ce99e09c/BuildingtheFutureTransmissionGrid.pdf#page=8
HTML attribution<a href="https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics#transmission-cable-transformer-waiting-times">American Mineral Registry</a>. The IEA’s 2025 transmission report found cable procurement generally took two to three years, large power transformers up to four years, and direct-current cables more than five years. Survey of leading industry participants; not universal durations or a mine lead-time statistic. Original evidence: <a href="https://www.iea.org/files/744ff0bb-905a-4f9f-83e3-2d04ce99e09c/BuildingtheFutureTransmissionGrid.pdf#page=8">IEA Transmission Grid 2025, p. 8</a>.

Supporting table · Permanent finding link · Matching CSV · IEA Transmission Grid 2025, p. 8

Mid-2030s transmission investment requirements are materially above 2023 spending

IEA reports worldwide power transmission investment reached USD 140 billion in 2023 and says it would need to exceed USD 200 billion annually by the mid-2030s under today’s policies, or USD 250–300 billion in its emissions-goal scenarios.

Transmission spending, not all grids, a raw-metal market forecast or guaranteed future expenditure.

American Mineral Registry. IEA reports worldwide power transmission investment reached USD 140 billion in 2023 and says it would need to exceed USD 200 billion annually by the mid-2030s under today’s policies, or USD 250–300 billion in its emissions-goal scenarios. Transmission spending, not all grids, a raw-metal market forecast or guaranteed future expenditure. https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics#global-transmission-capital-requirement Original evidence: https://www.iea.org/files/744ff0bb-905a-4f9f-83e3-2d04ce99e09c/BuildingtheFutureTransmissionGrid.pdf#page=7, https://www.iea.org/files/744ff0bb-905a-4f9f-83e3-2d04ce99e09c/BuildingtheFutureTransmissionGrid.pdf#page=8
HTML attribution<a href="https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics#global-transmission-capital-requirement">American Mineral Registry</a>. IEA reports worldwide power transmission investment reached USD 140 billion in 2023 and says it would need to exceed USD 200 billion annually by the mid-2030s under today’s policies, or USD 250–300 billion in its emissions-goal scenarios. Transmission spending, not all grids, a raw-metal market forecast or guaranteed future expenditure. Original evidence: <a href="https://www.iea.org/files/744ff0bb-905a-4f9f-83e3-2d04ce99e09c/BuildingtheFutureTransmissionGrid.pdf#page=7">IEA Transmission Grid 2025, p. 7</a> · <a href="https://www.iea.org/files/744ff0bb-905a-4f9f-83e3-2d04ce99e09c/BuildingtheFutureTransmissionGrid.pdf#page=8">IEA Transmission Grid 2025, p. 8</a>.

Supporting table · Permanent finding link · Matching CSV · IEA Transmission Grid 2025, p. 7 · IEA Transmission Grid 2025, p. 8

Data and downloads

No account or form is required. CSV tables preserve the article’s units, evidence periods and source estimates.

Grid model boundaries (CSV)

Iea 2021 grid metal components (CSV)

Iea 2021 grid metal totals (CSV)

Iea 2026 copper demand by grid scenario (CSV)

Iea 2026 historical change (CSV)

Expanded research datasets

IEA 2026 detailed copper demand by use, scenario and year (CSV)

2021–25 copper demand change by end-use row (CSV)

2020–40 grid metal increase by component in the 2021 outlook (CSV)

Component procurement, mass and cost evidence (CSV)

Grid investment, connection queue and workforce benchmarks (CSV)

Cite this page

Keep the original source edition, unit and observation or scenario period alongside the number.

American Mineral Registry. "Electricity Grid Copper and Aluminium Demand Statistics." American Mineral Registry, November 2026. https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics/
<a href="https://americanmineralregistry.com/research/electricity-grid-copper-aluminium-demand-statistics/">Electricity grid metal demand</a> (American Mineral Registry, November 2026)

  • Copper ore gradeTrack twenty-six years of Chilean copper ore grades and compare the ore needed per tonne of copper. Includes process grades and reproducible calculations.
  • Mineral reserves and productionCompare reserves and annual mine output for six minerals using USGS world and country data. See each ratio, product unit and reserve classification.
  • Copper supply and demandRead the underlying production and demand series.
  • Copper supply gap forecastsCompare the IEA, S&P and Payne Institute outlooks.