American Mineral RegistryResearch & data

Copper Supply Gap Forecasts: What the Numbers Measure

Updated

Quick Answer

Three copper outlooks put different quantities behind the words supply gap. The IEA reports an approximately 25% gap in 2035 against primary copper requirements in its Stated Policies Scenario. S&P Global reports a 10 million metric ton market shortfall in 2040 on its study trajectory. The Payne Institute estimates 16.1 million metric tons per year of additional mined output still to build for its 2050 baseline. The target years, demand assumptions and supply counted differ in all three. (IEA Outlook (accessed), Nov 2026) (S&P Global study release, Jan 2026) (Payne Institute investment note, Oct 2026)

Additional projects do not close the modeled copper gap. For the IEA 2035 STEPS case, moving from 20.7 Mt base-case mine supply to 24.5 Mt high-case supply closes approximately 57.58% of the 6.6 Mt primary copper gap; 2.8 Mt remains. Same IEA scenario and same primary requirement boundary; conditional project cases. (IEA original downloadable chart.) Cite this finding.

On this page
  1. Quick Answer
  2. Key Takeaways
  3. Source comparison
  4. What does each forecast compare?
  5. What do the IEA’s 2035 assumptions imply?
  6. What does S&P’s 10-million-ton 2040 shortfall measure?
  7. Why does the Payne Institute report 19.3, 16.1 and 4.6 Mt?
  8. How to use these benchmarks in a research brief
  9. How much of the IEA’s 2035 copper gap would the high case close?
  10. Why can the copper mine supply pipeline decline after 2030?
  11. How sensitive is copper mine investment to capital intensity?
  12. What should an author check before describing a copper shortage?
  13. Methodology and sources

Key Takeaways

  • 6.6 million metric tons from the IEA chart. Its rounded 2035 Stated Policies primary requirement of 27.3 Mt less 20.7 Mt of projected base-case mine supply implies 24.18%. The report separately describes the gap at roughly 25%. (IEA source chart (accessed), Nov 2026)
  • 10 Mt is the S&P 2040 market gap. It estimates 42 Mt of demand and projects an increase in recycled copper scrap to 10 Mt by that year. (S&P Global release, Jan 2026)
  • Payne reports separate 2050 gaps for different supply sets. At 37.1 Mt per year of mined demand, the gap is 19.3 Mt against the 2018 fleet, 16.1 Mt after counting more recent output and 4.6 Mt against the upper identified pipeline. (Payne Institute, sections 2 and 3, Oct 2026)

Which changes the IEA copper gap more, higher project output or lower demand?

The IEA’s high project case adds 3.8 Mt Cu to its 2035 copper output assumptions, 1.9 times the spread between the lowest and highest primary requirements. Even under the high production case, output would need to rise a further 6.53%, 11.43% or 14.69% to meet Current Policies, Stated Policies or High Demand requirements, respectively. (IEA, expected mine supply and primary copper requirements by scenario, Nov 2026).

Calculated comparisonResultCalculation
Current Policies uplift from high production6.53%(A ÷ D − 1) × 100
Stated Policies uplift from high production11.43%(B ÷ D − 1) × 100
High Demand uplift from high production14.69%(C ÷ D − 1) × 100
Spread between residuals, High Demand versus Current Policies2.0 Mt CuC − A
Increase between the two project production cases3.8 Mt CuD − E
Project supply swing divided by the demand case spread1.9 times(D − E) ÷ (C − A)

The common starting point is 24.5 million tonnes of contained copper in the high production case. The required uplift divides each residual by that production base. A gap expressed as a percentage of requirements uses a different denominator and produces a smaller percentage.

How to use this comparison

The high production case moves the modeled balance 3.8 million tonnes compared with base supply. The entire range from Current Policies to High Demand moves it 2.0 million tonnes. These are alternative assumptions, so the comparison ranks their arithmetic effects. It assigns neither probability nor cost. Related evidence on Mine Development Lead Times: Discovery to First Production.

Reproduce the numbers

Each letter in the calculation maps to a source value below. Calculate from the displayed source values and round the result only at the end. The download records the source file, row, field and formula.

InputWhat is measuredSource valueExact source row and field
ACurrent Policies requirements26.1Current Policies (CPS) · Primary requirements (Mt Cu)
BStated Policies requirements27.3Stated Policies (STEPS) · Primary requirements (Mt Cu)
CHigh Demand requirements28.1High Demand (HDS) · Primary requirements (Mt Cu)
DHigh production case24.5Current Policies (CPS) · High-case supply (Mt Cu)
EBase production case20.7Current Policies (CPS) · Base supply (Mt Cu)

Download the calculation and source rows (CSV)

Cite this comparison

The IEA’s high project case adds 3.8 Mt Cu to its 2035 copper output assumptions, 1.9 times the spread between the lowest and highest primary requirements. Even under the high production case, output would need to rise a further 6.53%, 11.43% or 14.69% to meet Current Policies, Stated Policies or High Demand requirements, respectively. American Mineral Registry calculation from IEA, expected mine supply and primary copper requirements by scenario. 2035 primary copper requirements and high production case in the IEA 2026 outlook. https://americanmineralregistry.com/research/copper-supply-gap-forecast-comparison#amr-reader-analysis

HTML attribution

<a href="https://americanmineralregistry.com/research/copper-supply-gap-forecast-comparison#amr-reader-analysis">Which changes the IEA copper gap more, higher project output or lower demand?</a>

What does each forecast compare?

A copper statistic can be about the market as a whole, an amount that must be mined after accounting for secondary supply, or the capacity that a defined group of mines can still deliver. Even a common unit such as million metric tons can hide all three differences. Use the target year, source edition, demand case and counted supply together.

Copper forecast scope. The IEA compares existing and announced mine supply with a 2035 primary requirement. S&P uses a 2040 market outlook. Payne uses the 2018 mine fleet plus later additions in its 2050 forward case.
Figure 1: The time horizon and supply boundary identify the estimate before its size is interpreted. Source: IEA Global Critical Minerals Outlook 2026. Chart drawn by American Mineral Registry from the source figures, checked 25 Nov 2026.
View chart data

The study population, projection year and supply coverage determine what its gap means.

Three sources measure three different copper gaps
StudyTargetSupply boundary
IEA Global Critical Minerals Outlook 20262035Existing and announced mine supply, base case
S&P Copper in the Age of AI2040Market supply, with expected growth in recycled scrap
Payne Institute 2026 investment note20502018 mine fleet plus 3.2 Mt per year added since 2018

Values and definitions are also readable in HTML. Source precision and scope apply.

IEA Global Critical Minerals Outlook 2026 Original primary evidence

Download this figure (SVG)

Copper forecast crosswalk
Original studyTarget yearDemand scenarioRequirement boundaryProduction countedHeadline or reproducible result
IEA Global Critical Minerals Outlook 20262035Stated Policies ScenarioPrimary requirement after deducting secondary supplyExisting and announced mine supply, base case25% headline; 6.6 Mt from rounded chart values
S&P Copper in the Age of AI2040Study outlook on current trajectoryGlobal copper demand, 42 MtMarket supply, with expected growth in recycled scrap10 Mt market shortfall in the release
Payne Institute 2026 investment note2050Business as usual baselineMined copper demand, 37.1 Mt per year2018 mine fleet plus 3.2 Mt per year added since 201816.1 Mt per year additional output in the forward case

IEA source · IEA source · S&P Global study release · Payne Institute · Download matching CSV

Copper mined at the ore stage, copper refined into a usable product, and copper contained in recovered scrap are related measures with different roles in a forecast. The IEA calculates primary requirements by deducting secondary supply from its total demand projection. S&P frames a market gap alongside expected growth in recycling. Payne’s note begins with its underlying study’s mined demand and asks how much new output is needed beyond a specified mine fleet. A percentage based on total demand therefore answers a different question from a percentage based on primary demand. (IEA methodology, Annex p. 345 (accessed), Nov 2026)

What do the IEA’s 2035 assumptions imply?

The underlying IEA chart shows 20.7 Mt of project-based mine supply in the base case. The high-production case adds 3.8 Mt, reaching 24.5 Mt in the rounding used by the chart. Its stacked demand inputs are 26.1 Mt under Current Policies, an additional 1.2 Mt under Stated Policies, and another 0.8 Mt in High Demand. AMR reconstructs the three requirements as 26.1, 27.3 and 28.1 Mt. All values are annual volumes of contained copper in 2035. (IEA 2035 copper chart data and notes (accessed), Nov 2026)

IEA 2035 primary copper requirements are 26.1 Mt Current Policies, 27.3 Mt Stated Policies and 28.1 Mt High Demand. Base mine supply is 20.7 Mt in each comparison.
Figure 2: The base-case supply is compared with three primary demand scenarios at the same date. Source: IEA 2035 copper scenario chart. Chart drawn by American Mineral Registry from the source figures, checked 25 Nov 2026.
View chart data

Rounded original chart inputs, million metric tons of contained copper.

What it would take to meet IEA primary needs in 2035
ScenarioPrimary requirements (Mt)IEA base mine supply (Mt)
Current Policies (CPS)26.120.7
Stated Policies (STEPS)27.320.7
High Demand (HDS)28.120.7

Values and definitions are also readable in HTML. Source precision and scope apply.

IEA 2035 copper scenario chart Original primary evidence

Download this figure (SVG)

IEA 2035 scenario balance
IEA 2035 demand scenarioPrimary requirements (Mt Cu)Base supply (Mt Cu)Base gap (Mt Cu)Base gap (%)High-case supply (Mt Cu)High-case gap (Mt Cu)High-case gap (%)
Current Policies (CPS)26.120.75.420.6924.51.66.13
Stated Policies (STEPS)27.320.76.624.1824.52.810.26
High Demand (HDS)28.120.77.426.3324.53.612.81

IEA source · Download matching CSV

For the Stated Policies case, 27.3 minus 20.7 equals 6.6 Mt. That is 24.18% of the displayed primary requirement. The IEA separately describes the gap as approximately 25%. AMR keeps the producer’s headline and the calculation from rounded chart components as distinct figures. The higher supply case cuts the displayed Stated Policies gap to 2.8 Mt, or 10.26%, and still leaves 1.6 Mt against Current Policies. These calculations describe the scenario arithmetic. They do not establish that the additional production is committed.

The IEA says the corresponding projected copper gap narrowed from around 30% in its prior assessment to 25% in the 2026 outlook. The report attributes the improving balance in part to more anticipated projects. That comparison is about successive projections. To see the historical mining and refining data alongside the IEA vintages, read AMR’s copper production and demand statistics. IEA 2026 Outlook.

What does S&P’s 10-million-ton 2040 shortfall measure?

S&P Global’s 2026 study release projects 42 million metric tons of copper demand in 2040 and a 10 million metric ton shortfall if supply stays on the study’s modeled trajectory. The release also gives a projected 2030 production peak at 33 million metric tons. That peak is from a separate year. Subtracting it from 2040 demand would mix the production peak and the year used in the shortfall estimate.

Sp copper outlook metrics
MeasureTarget yearMillion metric tonsScope
Global copper demand204042Projected demand in the S&P release
Global production peak203033Projected production peak in the S&P release
Market shortfall204010Study headline shortfall on current trajectory
Recycled copper scrap204010Projected amount in the S&P release

S&P Global study release · Download matching CSV

The release projects recycled copper scrap to rise from around 4 million to 10 million metric tons by 2040. It describes the projected shortfall alongside that recycling growth. Its demand drivers include conventional uses as well as electrification, data centers and defense. The public release gives rounded quantities and describes the 2040 gap as approximately a quarter of demand. To reproduce the precise underlying model, a researcher would need the source’s detailed unrounded demand and supply series. S&P Global producer release.

Why does the Payne Institute report 19.3, 16.1 and 4.6 Mt?

The Payne Institute starts with 37.1 Mt per year of baseline 2050 mined copper demand. It estimates that mines operating in 2018 will supply 17.8 Mt per year in 2050. The difference is 19.3 Mt per year. It then credits 3.2 Mt per year from mines opened or expanded after 2018, assuming that supply persists to 2050. The gap still to build from its forward starting point becomes 16.1 Mt per year. (Payne Institute, sections 2.1–2.2 and Table 1, Oct 2026)

Payne Institute 2050 gaps in million tonnes per year: 19.3 against the 2018 fleet, 16.1 after additions to 2025, 4.6 against the upper identified-project supply case.
Figure 3: The narrower residual reflects a broader set of projects counted in the modeled supply. Source: Payne Institute, sections 2–3. Chart drawn by American Mineral Registry from the source figures, checked 25 Nov 2026.
View chart data

2050 mined copper, million metric tons each year. Separate model comparisons.

Payne’s remaining gap depends on the supply counted
DefinitionGap (Mt/yr)
Full-period gap19.3
Forward baseline gap16.1
Gap above upper pipeline4.6

Values and definitions are also readable in HTML. Source precision and scope apply.

Payne Institute, sections 2–3 Original primary evidence

Download this figure (SVG)

Payne 2050 gap bridge
MetricMillion tonnes copper per yearMeaning
Baseline mined demand37.12050 mined copper requirement
Output from 2018 mines17.8Modeled 2050 production from the 2018 mine cohort
Full-period gap19.337.1 minus 17.8
Capacity added since 20183.22025 addition assumed to persist to 2050
Forward baseline gap16.119.3 minus 3.2
Upper pipeline supply32.5Modeled 2050 output including identified projects
Gap above upper pipeline4.637.1 minus 32.5

Payne Institute · Download matching CSV

The paper separately estimates that its upper identified-project supply trajectory could reach 32.5 Mt per year in 2050 if the assumed start dates materialize. That leaves 4.6 Mt per year below the same demand level. The upper trajectory includes projects that need development. The 16.1 figure therefore remains relevant to the investment required for future supply, while the 4.6 figure is relevant to the portion outside the upper identified pipeline.

The paper’s other cases supply a check on sensitivity. Using USGS’s rounded 23.0 Mt estimate of 2025 mine output instead of the underlying 23.5 Mt world benchmark in the Payne model reduces inferred post-2018 additions to 2.7 Mt. The forward gap then rises from 16.1 to 16.6 Mt per year. The example identifies the source change and shows why even two values inside one model can differ. Payne Institute, section 2.2.

How to use these benchmarks in a research brief

State the forecast horizon and source before using the gap. Include the demand measure and which existing, prospective and recycled output is counted. If converting to a percentage, divide by the requirement stated for that exact estimate. If comparing years, distinguish revisions for a common target year from a comparison of forecasts at different target years. These checks catch several common errors even before the reader sees the underlying spreadsheet.

How much of the IEA’s 2035 copper gap would the high case close?

The high-production case offers one of the most useful ways of evaluating a gap because it holds the demand assumptions fixed while changing the represented mine-project pipeline. All three IEA demand cases can be evaluated against the same 20.7 Mt base supply and 24.5 Mt high-case supply in the published chart. The extra 3.8 Mt of output closes much more of the smaller Current Policies gap than the larger High Demand gap. Against the Stated Policies case, 3.8 of the original 6.6 Mt gap is closed, or 57.58%, and 2.8 Mt remains.

Additional projects versus remaining 2035 gap. High-case uplift is 3.8 Mt in every demand scenario.
Figure 4: High-case uplift is 3.8 Mt in every demand scenario. Sources: IEA original downloadable chart. See the full supporting table below.
View chart data

High-case uplift is 3.8 Mt in every demand scenario.

Additional projects versus remaining 2035 gap
Demand caseAdditional supply (Mt)Residual gap (Mt)
Current Policies3.81.6
Stated Policies3.82.8
High Demand3.83.6

Figures retain the source units and definitions.

IEA original downloadable chart

Download chart data · Download chart SVG

Scroll the full table to compare columns and rows. The complete data are also available as a CSV.

Additional announced supply versus remaining demand requirement
ScenarioPrimary requirement (Mt)Base production (Mt)High-case production (Mt)Increment from high case (Mt)Base gap (Mt)Base gap closed (%)Remaining gap (Mt)Additional output relative to high case (%)
Current Policies (CPS)26.120.724.53.805.470.371.66.53
Stated Policies (STEPS)27.320.724.53.806.657.582.811.43
High Demand (HDS)28.120.724.53.807.451.353.614.69

IEA original downloadable chart · Download matching CSV

From IEA 2035 figure: high minus base; uplift divided by base gap; residual divided by high case supply. Conditional project cases, not forecasts of shortage.

The “gap closed” percentage uses the original demand-minus-base-output gap as denominator. The additional-output percentage instead uses the high-case supply as denominator. Neither is the same measure as the unmet share of demand, which remains in the earlier table. For STEPS, the three results answer three different questions: what portion of the original gap would disappear, how much higher than high-case mine output the supply would have to be, and what share of primary requirements would remain uncovered. The results are derived from the rounded source chart, so keep the original IEA headline of roughly one quarter separate from precise arithmetic on displayed numbers. IEA 2035 primary supply requirements chart.

Why can the copper mine supply pipeline decline after 2030?

In the 2026 Annex, historical mine output is 23,227 kt in 2025 and the existing and announced base case reaches 24,571 kt in 2030. By 2040 it falls to 17,183 kt, a decline of 7,388 kt, or 30.07% relative to 2030. This differs from economic models which assume new mine investment will respond to prices, policy or rising demand. The IEA base case describes the specific project set and its expected output; it is not a conclusion that total real-world output will inevitably decline by that amount.

IEA base case supply by stage across vintages
Supply stage2025 historical (kt Cu)2030 base case (kt Cu)2040 base case (kt Cu)2030 to 2040 change (kt)2030 to 2040 relative change (%)
Mine output232272457117183-7388-30.07
Refined output279553638333710-2673-7.35

IEA Critical Minerals Outlook 2026, p. 348 · Download matching CSV

Annex table: 2040 base case minus 2030, divided by 2030. Stage totals are not subtractable as an apparent consumption balance.

The same annex shows different refinery production volumes. Refining may use secondary inputs and concentrate from multiple origins. Comparing separate-stage totals as if they were the two sides of one commodity balance would incorrectly turn refining-minus-mining into a primary deficit. A primary requirement is calculated after considering secondary supply, whereas a total refined demand comparison has another boundary. IEA also excludes direct scrap use from its refined copper demand series. IEA annex copper supply and copper demand.

New mine supply is also not the same as reserves or resources. An announced prospect may require permitting, engineering, finance and a lengthy construction and ramp-up period before a saleable concentrate or cathode is produced. The mine development timeline study compares historical cohorts and distinguishes operating properties from projects with projected dates. The reserves and production study explains why a country's reserve share should not be substituted for its share of annual output.

How sensitive is copper mine investment to capital intensity?

The Payne Institute uses several capital-intensity assumptions in its investment comparison. This permits a useful, transparent sensitivity exercise independent of any project-specific valuation. At a forward capacity requirement of 16.1 Mt/y, a source assumption of USD 25,000 per annual tonne of capacity (2024 dollars) implies a simple multiplication of USD 402.5 billion. At USD 18,916 or USD 31,318 per annual tonne the same capacity implies different capital requirements. The full-period 19.3 Mt/y requirement is a different boundary and should not be added to the forward amount.

Illustrative capital multiplication from Payne Institute inputs
Capacity boundaryRequired capacity (Mt/y)Assumed capital intensity (2024 USD per annual tonne)AMR multiplication (2024 USD bn)
Forward capacity16.118916304.5
Forward capacity16.125000402.5
Forward capacity16.131318504.2
Full-period capacity19.318916365.1
Full-period capacity19.325000482.5
Full-period capacity19.331318604.4

Payne Institute, copper investment gap · Download matching CSV

Payne Table 1 rounded source inputs. AMR multiplies millions of annual tonnes by USD per annual tonne, divided by 1,000. May differ slightly from source totals using unrounded inputs; not a project estimate or annual spend.

Each result is calculated by multiplying the rounded million-tonne annual capacity number by the stated dollars per annual tonne and dividing by 1,000 to express billions of dollars. The source's own results can differ slightly because its displayed inputs are rounded. It is not a cash-flow model: no timing of capital expenditures, financing costs, depreciation, exchange rates, operating costs, inflation, price trajectory or specific mine feasibility is assumed. The sensitivity can illustrate why the same tonnage scenario may support materially different investment figures, but it cannot predict the amount any developer will spend. Payne Institute, investment gap, Table 1.

The authors’ baseline development cost excludes sustaining capital, smelters and refineries, exploration and financing. It uses 2024 dollars and, at base, assumes full realisation of rated capacity without an escalation or overrun allowance. The 26-project average capital intensity is USD 22,359 per annual tonne. Holding that benchmark constant, the hybrid, full electrification plus grid and net-zero demand cases lead to very different forward capacity requirements. The full-period baseline is provided separately rather than added to the forward baseline.

Payne scenario boundary and implied development capital
Scenario or periodAdditional annual mine capacity (Mt/y)Common capital intensity (2024 USD per annual tonne)Implied development capital (2024 USD bn)
Baseline16.122359360.0
Hybrid fleet16.822359375.6
Full EV + grid24.722359552.3
Net zero70.7223591580.8
2018–2050 full period baseline19.322359431.5

Payne Institute, copper investment gap · Download matching CSV

Table 1; source rounded capacities multiplied by fixed 26-project average intensity. Excludes sustaining, refining, exploration and finance costs. Baseline is 2026 onward except clearly labeled full period.

The resulting dollar comparisons are not the cost of building an entire electrified economy. They relate to additional mine capacity within the Payne model. The model separately considers recycling, existing mine output, additions through 2025, stockpile leaching, realised utilisation and cost escalation; it does not imply that the capital-intensity assumption is known with certainty. Its source table displays USD 360 billion for the forward baseline and about USD 1.58 trillion for the net-zero scenario at the 26-project average. Payne Institute, model and Table 1.

What should an author check before describing a copper shortage?

First specify the counterfactual. A gap comparing existing and announced mines with primary requirements asks how much additional primary supply may be needed if demand develops on that path. A broader market supply shortfall can already include scrap, changes in demand, or other supply assumptions. A mine construction requirement may include replacement of depleting mines, not merely the increase from today's demand. Even the word deficit may refer to stocks and market balance within a calendar year rather than capacity needed decades from now.

S&P's January 2026 public release gives its 2040 demand headline of 42 Mt and shortfall of 10 Mt along with its trajectory and sector drivers. These figures should be attributed to that particular study, not described as a consensus or used to reconstruct sector-level quantities absent from the public release. The complete S&P scenario workbook was not used here. The cited IEA and Payne cases quantify different boundaries and years. An analyst cannot calculate a reliable average across them, since both their numerators and denominators differ. S&P Global study announcement.

Finally, consider response mechanisms without presuming their magnitude. Recycling and substitution may moderate primary requirements; additional mines, expansions, improved recovery and processing changes may add output. Ore grade changes may require additional material movement and capital for a given amount of recovered copper. These are distinct mechanisms with different time horizons, not interchangeable tonnes that can be freely credited to close the gap. The copper grade dataset quantifies that relationship under explicit recovery assumptions, while the grid metals dataset separates electricity-network copper demand from other end uses.

Methodology and sources

The expanded comparisons retain original source periods and row-level source references. Formulas, scope and precision are documented immediately beside each table, in the downloadable methods and source-cell ledger. Rounded primary values are not treated as exact unrounded observations.

AMR reviewed the IEA outlook and base case, the underlying IEA stacked chart data, the S&P Global January 8, 2026 release and the Payne Institute’s October 26, 2026 commentary. The IEA table sums demand increments by scenario and computes requirement less supply. The S&P table transcribes only the quantities and scopes stated in its public release. The Payne bridge follows the explicit mine cohorts and pipeline arithmetic. The tables retain all three producer definitions.

Glossary

  • Primary requirement: Demand remaining after secondary copper supply is deducted in the IEA model.
  • Secondary supply: Copper supplied from recovered materials such as scrap under the study’s accounting method.
  • Stated Policies Scenario: The IEA’s STEPS demand scenario used in its 2035 headline comparison.
  • Contained copper: The mass of copper in a material stream, excluding the mass of the non-copper portion.
  • Mine fleet: The group of mines selected as the baseline for a forecast. Payne starts with mines operating in 2018.
  • Forward baseline gap: Payne’s additional annual capacity requirement after accounting for production added since 2018.

Sources

Cite a specific finding

Copy the exact comparison with its period, scope and original evidence.

The three copper outlooks measure different supply gaps

The IEA’s approximately 25% 2035 primary supply gap, S&P’s 10 Mt 2040 market shortfall and Payne’s 16.1 Mt per year 2050 forward mine gap use different demand and supply definitions.

Compare each estimate with the stated year, scenario and included supply.

American Mineral Registry. The IEA’s approximately 25% 2035 primary supply gap, S&P’s 10 Mt 2040 market shortfall and Payne’s 16.1 Mt per year 2050 forward mine gap use different demand and supply definitions. Compare each estimate with the stated year, scenario and included supply. https://americanmineralregistry.com/research/copper-supply-gap-forecast-comparison#three-copper-gap-definitions Original evidence: https://www.iea.org/reports/global-critical-minerals-outlook-2026/outlook, https://press.spglobal.com/2026-01-08-Substantial-Shortfall-in-Copper-Supply-Widens-as-the-Race-for-AI-and-Growing-Defense-Spending-Add-to-Accelerating-Demand,-New-S-P-Global-Study-Finds, https://payneinstitute.mines.edu/the-investment-gap-in-copper-mining/
HTML attribution<a href="https://americanmineralregistry.com/research/copper-supply-gap-forecast-comparison#three-copper-gap-definitions">American Mineral Registry</a>. The IEA’s approximately 25% 2035 primary supply gap, S&amp;P’s 10 Mt 2040 market shortfall and Payne’s 16.1 Mt per year 2050 forward mine gap use different demand and supply definitions. Compare each estimate with the stated year, scenario and included supply. Original evidence: <a href="https://www.iea.org/reports/global-critical-minerals-outlook-2026/outlook">IEA source</a> · <a href="https://press.spglobal.com/2026-01-08-Substantial-Shortfall-in-Copper-Supply-Widens-as-the-Race-for-AI-and-Growing-Defense-Spending-Add-to-Accelerating-Demand,-New-S-P-Global-Study-Finds">S&amp;P Global study release</a> · <a href="https://payneinstitute.mines.edu/the-investment-gap-in-copper-mining/">Payne Institute</a>.

Supporting table · Permanent finding link · Matching CSV · IEA source · S&P Global study release · Payne Institute

The rounded IEA chart implies a 6.6 Mt gap

The IEA’s 2035 chart gives a base mine supply of 20.7 Mt and a Stated Policies primary requirement of 27.3 Mt. AMR calculates 6.6 Mt, or 24.18% of the displayed requirement.

The IEA separately summarizes the gap at approximately 25%. Computed from rounded chart inputs.

American Mineral Registry. The IEA’s 2035 chart gives a base mine supply of 20.7 Mt and a Stated Policies primary requirement of 27.3 Mt. AMR calculates 6.6 Mt, or 24.18% of the displayed requirement. The IEA separately summarizes the gap at approximately 25%. Computed from rounded chart inputs. https://americanmineralregistry.com/research/copper-supply-gap-forecast-comparison#iea-copper-2035-rounded-chart-gap Original evidence: https://www.iea.org/data-and-statistics/charts/expected-mine-supply-from-existing-and-announced-projects-and-primary-supply-requirements-for-copper-by-scenario-2035
HTML attribution<a href="https://americanmineralregistry.com/research/copper-supply-gap-forecast-comparison#iea-copper-2035-rounded-chart-gap">American Mineral Registry</a>. The IEA’s 2035 chart gives a base mine supply of 20.7 Mt and a Stated Policies primary requirement of 27.3 Mt. AMR calculates 6.6 Mt, or 24.18% of the displayed requirement. The IEA separately summarizes the gap at approximately 25%. Computed from rounded chart inputs. Original evidence: <a href="https://www.iea.org/data-and-statistics/charts/expected-mine-supply-from-existing-and-announced-projects-and-primary-supply-requirements-for-copper-by-scenario-2035">IEA source</a>.

Supporting table · Permanent finding link · Matching CSV · IEA source

Three numbers in the same Payne model reflect different supply sets

Against 37.1 Mt per year of 2050 mined demand, Payne’s baseline gap is 19.3 Mt against 2018 mines, 16.1 Mt after crediting post-2018 additions and 4.6 Mt against the upper identified-project supply curve.

The differences in each comparison reflect the mines or projects counted in that version of supply.

American Mineral Registry. Against 37.1 Mt per year of 2050 mined demand, Payne’s baseline gap is 19.3 Mt against 2018 mines, 16.1 Mt after crediting post-2018 additions and 4.6 Mt against the upper identified-project supply curve. The differences in each comparison reflect the mines or projects counted in that version of supply. https://americanmineralregistry.com/research/copper-supply-gap-forecast-comparison#payne-copper-2050-gap-bridge Original evidence: https://payneinstitute.mines.edu/the-investment-gap-in-copper-mining/
HTML attribution<a href="https://americanmineralregistry.com/research/copper-supply-gap-forecast-comparison#payne-copper-2050-gap-bridge">American Mineral Registry</a>. Against 37.1 Mt per year of 2050 mined demand, Payne’s baseline gap is 19.3 Mt against 2018 mines, 16.1 Mt after crediting post-2018 additions and 4.6 Mt against the upper identified-project supply curve. The differences in each comparison reflect the mines or projects counted in that version of supply. Original evidence: <a href="https://payneinstitute.mines.edu/the-investment-gap-in-copper-mining/">Payne Institute</a>.

Supporting table · Permanent finding link · Matching CSV · Payne Institute

Additional projects do not close the modeled copper gap

For the IEA 2035 STEPS case, moving from 20.7 Mt base-case mine supply to 24.5 Mt high-case supply closes approximately 57.58% of the 6.6 Mt primary copper gap; 2.8 Mt remains.

Same IEA scenario and same primary requirement boundary; conditional project cases.

American Mineral Registry. For the IEA 2035 STEPS case, moving from 20.7 Mt base-case mine supply to 24.5 Mt high-case supply closes approximately 57.58% of the 6.6 Mt primary copper gap; 2.8 Mt remains. Same IEA scenario and same primary requirement boundary; conditional project cases. https://americanmineralregistry.com/research/copper-supply-gap-forecast-comparison#copper-high-case-gap-closure Original evidence: https://www.iea.org/data-and-statistics/charts/expected-mine-supply-from-existing-and-announced-projects-and-primary-supply-requirements-for-copper-by-scenario-2035
HTML attribution<a href="https://americanmineralregistry.com/research/copper-supply-gap-forecast-comparison#copper-high-case-gap-closure">American Mineral Registry</a>. For the IEA 2035 STEPS case, moving from 20.7 Mt base-case mine supply to 24.5 Mt high-case supply closes approximately 57.58% of the 6.6 Mt primary copper gap; 2.8 Mt remains. Same IEA scenario and same primary requirement boundary; conditional project cases. Original evidence: <a href="https://www.iea.org/data-and-statistics/charts/expected-mine-supply-from-existing-and-announced-projects-and-primary-supply-requirements-for-copper-by-scenario-2035">IEA original downloadable chart</a>.

Supporting table · Permanent finding link · Matching CSV · IEA original downloadable chart

The announced-mine pipeline falls after 2030 in the base case

IEA’s base-case global copper mine output falls from 24,571 kt in 2030 to 17,183 kt in 2040, a 30.07% decline in the represented project pipeline.

IEA 2026 Annex base case, not an unconditional forecast of actual global output.

American Mineral Registry. IEA’s base-case global copper mine output falls from 24,571 kt in 2030 to 17,183 kt in 2040, a 30.07% decline in the represented project pipeline. IEA 2026 Annex base case, not an unconditional forecast of actual global output. https://americanmineralregistry.com/research/copper-supply-gap-forecast-comparison#existing-project-copper-decline Original evidence: https://www.iea.org/files/19c60aa0-ee07-4a20-a138-33c967ac5008/GlobalCriticalMineralsOutlook2026.pdf#page=348
HTML attribution<a href="https://americanmineralregistry.com/research/copper-supply-gap-forecast-comparison#existing-project-copper-decline">American Mineral Registry</a>. IEA’s base-case global copper mine output falls from 24,571 kt in 2030 to 17,183 kt in 2040, a 30.07% decline in the represented project pipeline. IEA 2026 Annex base case, not an unconditional forecast of actual global output. Original evidence: <a href="https://www.iea.org/files/19c60aa0-ee07-4a20-a138-33c967ac5008/GlobalCriticalMineralsOutlook2026.pdf#page=348">IEA Critical Minerals Outlook 2026, p. 348</a>.

Supporting table · Permanent finding link · Matching CSV · IEA Critical Minerals Outlook 2026, p. 348

Demand assumptions change the mine-capacity requirement

At constant 2024-dollar capital intensity of USD 22,359 per annual tonne, Payne’s rounded 16.1 Mt/y forward baseline implies about USD 360.0 billion; its 70.7 Mt/y net-zero case implies about USD 1,580.8 billion.

AMR calculation of rounded Payne Table 1 inputs, excluding sustaining, processing and financing capital.

American Mineral Registry. At constant 2024-dollar capital intensity of USD 22,359 per annual tonne, Payne’s rounded 16.1 Mt/y forward baseline implies about USD 360.0 billion; its 70.7 Mt/y net-zero case implies about USD 1,580.8 billion. AMR calculation of rounded Payne Table 1 inputs, excluding sustaining, processing and financing capital. https://americanmineralregistry.com/research/copper-supply-gap-forecast-comparison#payne-mining-cost-case-boundaries Original evidence: https://payneinstitute.mines.edu/the-investment-gap-in-copper-mining/
HTML attribution<a href="https://americanmineralregistry.com/research/copper-supply-gap-forecast-comparison#payne-mining-cost-case-boundaries">American Mineral Registry</a>. At constant 2024-dollar capital intensity of USD 22,359 per annual tonne, Payne’s rounded 16.1 Mt/y forward baseline implies about USD 360.0 billion; its 70.7 Mt/y net-zero case implies about USD 1,580.8 billion. AMR calculation of rounded Payne Table 1 inputs, excluding sustaining, processing and financing capital. Original evidence: <a href="https://payneinstitute.mines.edu/the-investment-gap-in-copper-mining/">Payne Institute, copper investment gap</a>.

Supporting table · Permanent finding link · Matching CSV · Payne Institute, copper investment gap

Data and downloads

No account or form is required. CSV tables preserve the article’s units, evidence periods and source estimates.

Copper forecast crosswalk (CSV)

Iea 2035 scenario balance (CSV)

Payne 2050 gap bridge (CSV)

Sp copper outlook metrics (CSV)

Expanded research datasets

Additional announced supply versus remaining demand requirement (CSV)

IEA base case supply by stage across vintages (CSV)

Illustrative capital multiplication from Payne Institute inputs (CSV)

Payne scenario boundary and implied development capital (CSV)

Cite this page

Retain the original producer, observation or projection year, and scope when citing any figure.

American Mineral Registry. "Copper Supply Gap Forecasts: What the Numbers Measure." American Mineral Registry, November 2026. https://americanmineralregistry.com/research/copper-supply-gap-forecast-comparison/