Mine Development Lead Times: Discovery to First Production

Updated

Quick Answer

Two observed global benchmarks put mine development at roughly 16 to 17 years from discovery to first production. S&P Global reported 15.7 years across 127 completed mines in its earlier sample. The three published stage averages in the IEA’s study of major mines opened from 2010 through 2019 sum to 16.9 years. A U.S. estimate of almost 29 years comes from a different S&P cohort that included unfinished projects and used projected startup dates. (IEA global stage chart, May 2021) (S&P Global Market Intelligence, pp. 15 and 19, Jun 2024)

Development time is concentrated before building starts. For S&P Global’s 127 operating mines, discovery through studies averaged 11.9 years, decisions 1.5 and construction 2.3. Discovery through studies therefore accounted for 75.80% of the sum of rounded stage means. S&P 2024 sample; not permitting time or an estimate for an individual project. (S&P Global Mine Development Times 2024, p. 16.) Cite this finding.

On this page
  1. Quick Answer
  2. Key Takeaways
  3. Source comparison
  4. How long is each stage of mine development?
  5. Which mines took longer in the observed samples?
  6. Why do U.S. estimates range from 13 to almost 29 years?
  7. How should a mine timeline be cited?
  8. What percentage of mine-development time is spent before construction?
  9. What changes when unfinished projects enter a mine lead-time sample?
  10. Which named US resource projects were already decades old in 2024?
  11. Which benchmark should be used for copper, nickel or lithium planning?
  12. Methodology and sources

Key Takeaways

  • 12.5 years through feasibility. The IEA’s early phase accounts for 73.96% of AMR’s sum of its three stage averages. Construction planning and physical construction together add 4.4 years. (IEA stage chart, May 2021)
  • Nickel mine types differ. IEA’s historical means are 19.5 years for laterite and 12.8 for sulfide. The observed gap is 6.7 years, calculated by AMR. (IEA mineral chart, May 2021)
  • The global mine mix matters. Gold makes up 70 of 127 mines in the earlier S&P observed sample. The average is partly a description of that sample composition. (S&P Global Market Intelligence, p. 16, Jun 2024)
  • Three observed U.S. openings become 13 properties in the expanded sample. The reported U.S. average moves from about 13 years to almost 29 when the report adds projects with projected first production. (S&P Global Market Intelligence, pp. 17–19, Jun 2024)

How much of development time comes before construction?

Discovery, feasibility and construction planning account for 84.62% of the total time in the IEA’s rounded average stages for mines opened from 2010 through 2019. Those stages add to 14.3 years before construction starts. (IEA, global average lead times by stage, Nov 2026).

Calculated comparisonResultCalculation
Average stages before construction14.3 yearsA + B
All average stages added16.9 yearsA + B + C
Pre-construction share of the stage sum84.62%(A + B) ÷ (A + B + C) × 100
Pre-construction time per year of construction5.50 times(A + B) ÷ C

These are rounded average stages for mines that reached first production. Their sum is an arithmetic comparison. Project cohorts that include still inactive or undeveloped deposits answer a different question and should not be used to infer a permit duration.

How to use this comparison

When reviewing a claimed five year build, ask whether the clock starts at discovery, a construction decision or ground breaking. A short build schedule does not shorten exploration and feasibility work already completed. Related evidence on Copper Supply Gap Forecasts: What the Numbers Measure.

Reproduce the numbers

Each letter in the calculation maps to a source value below. Calculate from the displayed source values and round the result only at the end. The download records the source file, row, field and formula.

InputWhat is measuredSource valueExact source row and field
ADiscovery through feasibility12.5Discovery and exploration through feasibility · Mean years
BConstruction planning1.8Construction planning · Mean years
CConstruction to first output2.6Construction through first production · Mean years

Download the calculation and source rows (CSV)

Cite this comparison

Discovery, feasibility and construction planning account for 84.62% of the total time in the IEA’s rounded average stages for mines opened from 2010 through 2019. Those stages add to 14.3 years before construction starts. American Mineral Registry calculation from IEA, global average lead times by stage. IEA sample of mines entering production from 2010 through 2019. https://americanmineralregistry.com/research/mine-development-lead-time-statistics#amr-reader-analysis

HTML attribution

<a href="https://americanmineralregistry.com/research/mine-development-lead-time-statistics#amr-reader-analysis">How much of development time comes before construction?</a>

How long is each stage of mine development?

The IEA’s study reports 12.5 years from discovery and exploration through feasibility, 1.8 years of construction planning, and 2.6 years from construction to first production. These are group averages across major mines that reached production during the study window. The figures describe the entire development path, including geological work and project planning alongside construction. Feasibility is the point used to separate stages in this chart. A company’s own project milestones can be labelled differently. (IEA Reliable supply of minerals, May 2021)

IEA observed lead times in years: discovery and exploration through feasibility 12.5, construction planning 1.8, construction through first production 2.6.
Figure 1: Most of the mean elapsed time was measured by the IEA before the construction planning phase. Source: IEA global average lead times, 2010–2019. Chart drawn by American Mineral Registry from the source figures, checked 25 Nov 2026.
View chart data

IEA stage averages for major mines opened in 2010–2019, in years.

Most of the measured time comes before construction planning
StageAverage years
Discovery and exploration through feasibility12.5
Construction planning1.8
Construction through first production2.6

Values and definitions are also readable in HTML. Source precision and scope apply.

IEA global average lead times, 2010–2019 Original primary evidence

Download this figure (SVG)

IEA lead time stages
IEA stageMean yearsAMR share of stage sum (%)
Discovery and exploration through feasibility12.573.96
Construction planning1.810.65
Construction through first production2.615.38

IEA source · Download matching CSV

AMR adds the three reported means to obtain 16.9 years and divides each stage by that sum when calculating its share. The result uses the displayed decimal precision. The IEA analysis describes this as over 16 years from discovery to production. The ratio of the displayed means gives a clearer basis for a short statement about where elapsed time accumulated. A researcher estimating approval duration needs actual dates for submission, decisions and appeals as defined by the relevant authority or study.

Which mines took longer in the observed samples?

Among the five IEA groups, Australian lithium averaged 4 years and South American lithium averaged 7. Copper averaged 16.8 years, between the two IEA nickel values of 12.8 years for sulfide and 19.5 for laterite. The groups combine the effect of geography, deposit type, technology, approval processes and other project characteristics. A claim about one of those factors in isolation needs another study design. (IEA selected mineral lead-time chart, May 2021)

IEA lead times in years: Australian lithium 4, South American lithium 7, sulfide nickel 12.8, laterite nickel 19.5, copper 16.8.
Figure 2: The mine type and geographic grouping identify the benchmark as much as the commodity name. Source: IEA selected mineral lead times, 2010–2019. Chart drawn by American Mineral Registry from the source figures, checked 25 Nov 2026.
View chart data

Five IEA historical cohorts; years from discovery to first production.

Lead time differs by mine type and region
IEA groupAverage years
Lithium (Australia)4.0
Lithium (South America)7.0
Nickel (Sulfide)12.8
Nickel (Laterite)19.5
Copper16.8

Values and definitions are also readable in HTML. Source precision and scope apply.

IEA selected mineral lead times, 2010–2019 Original primary evidence

Download this figure (SVG)

IEA mineral lead times
IEA groupAverage yearsProduction opening cohort
Lithium (Australia)42010–2019
Lithium (South America)72010–2019
Nickel (Sulfide)12.82010–2019
Nickel (Laterite)19.52010–2019
Copper16.82010–2019

IEA source · Download matching CSV

S&P’s observed sample reports 16.2 years for 34 copper mines and 17.5 years for 13 nickel mines. Its nickel result combines mines under a broader category. The producer reports 15.2 years for gold, 15.8 for zinc and 15.7 across all 127 mines. The all-mines mean is the study’s reported aggregate. It cannot be recovered by giving gold, copper, nickel and zinc one vote apiece. Across different reports, check the mineral coding and the opening cohort before describing any difference as a change over time. (S&P Global Market Intelligence, pp. 15–16, Jun 2024)

Sp observed lead times
GroupMinesDiscovery through studies (years)Construction decision (years)Construction to startup (years)Published average years
Gold7011.91.22.115.2
Copper3412.41.42.416.2
Nickel1311.02.63.917.5
Zinc911.42.12.215.8
All mines12711.91.52.315.7

S&P Global report, p. 16 · Download matching CSV

S&P’s report also summarizes a smaller study of mine openings in 2020 through 2023 at 17.9 years. The observed samples have different selection windows and compositions. The article’s data file keeps them separate and labels the window in the same row as each statistic.

Lead time benchmarks
BenchmarkCohortYearsScope
IEA observed global estimateMajor mines that opened in 2010–201916.9AMR sum of three rounded stage means
S&P observed sample127 mines in the earlier opening cohort15.7Published mean, data compiled April 4, 2023
S&P newer opening sampleMines that opened 2020–202317.9Published mean for separate smaller sample, reported in June 2024 study
S&P expanded U.S. sample13 U.S. mines and projects out of 268 globalAlmost 29Observed and projected; 2030 assigned if a projected date was unavailable

IEA source · S&P Global report, p. 15 · S&P Global report, p. 19 · Download matching CSV

Why do U.S. estimates range from 13 to almost 29 years?

Only three U.S. mines appeared in the earlier S&P set of observed openings. They averaged about 13 years, versus about 16 for the eleven Canadian mines and 15 for the eleven Australian mines. S&P’s expanded analysis included properties still in development. It uses 13 U.S., 29 Canadian and 30 Australian properties inside a 268-property global sample. Its rounded averages for this broader comparison were almost 29, 27 and 20 years respectively. (S&P Global Market Intelligence, executive summary and pp. 17–19, Jun 2024)

U.S. evidence in S&P. Three observed mines had about 13 years of lead time. Thirteen properties in a completed and unfinished mix yielded almost 29 years with projected startups.
Figure 3: The expanded S&P result changes both the project population and the treatment of the end date. Source: S&P Global Market Intelligence, expanded cohort, p. 19. Chart drawn by American Mineral Registry from the source figures, checked 25 Nov 2026.
View chart data

S&P 2024 comparison of completed mines and the larger mixed sample.

The cohort changes the U.S. number
GroupCountAverage years
Observed U.S. openings3 minesAbout 13
U.S. expanded sample13 mines or projectsAlmost 29, with projected startups

Values and definitions are also readable in HTML. Source precision and scope apply.

S&P Global Market Intelligence, expanded cohort, p. 19 Original primary evidence

Download this figure (SVG)

Sp cohort comparison
CountryOperating sample countApprox. observed average yearsExpanded sample countApprox. expanded average years
United States31313Almost 29
Canada11162927
Australia11153020

S&P Global report, p. 17 · S&P Global report, p. 19 · S&P Global report, p. 6 · Download matching CSV

The expanded count column follows the narrative on page 19. The detailed status table on page 20 instead totals Australia 29 and Canada 30; see the source discrepancy and separate detailed comparison.

The expanded study uses a projected startup year where one was available in the data and 2030 where S&P lacked one. That makes the nearly 29-year figure conditional on the inputs the study used. The observed sample is conditional in another way: each property had already crossed the threshold into production. Long-running projects that had yet to reach that milestone sit outside that earlier average. For a completed-project benchmark, use the observed series. For a discussion of unfinished developments, give the broader cohort and its estimated end-date rule.

A public project announcement can use “started” for early construction and “first production” for an initial shipment. A research comparison is easier to replicate when it records both the discovery and production milestones verbatim, whether or not there are intermediate milestones. On an active project with no commissioning date, report elapsed time through the observation date as such. A completed lead time includes the actual first production endpoint.

How should a mine timeline be cited?

Put the mineral, sample, milestone and study edition in the same sentence as the number. The IEA’s 16.8 years is appropriate for its historical copper group. A statement about the effect of the permitting process needs a permit-specific clock. A schedule for a current project needs its own exploration, studies, authorizations, financing, construction and commissioning evidence. The stage and cohort tables allow editors to choose the relevant benchmark without treating a global sample as a project forecast.

What percentage of mine-development time is spent before construction?

The headline elapsed time is often described as an approval delay. That is a much narrower concept than the interval the two primary studies measure. Discovery through technical and economic study can encompass resource definition, exploration drilling, engineering, environmental studies and selection of a viable project design. Approvals, financing, infrastructure and construction readiness can overlap these activities. A company's investment decision is another milestone; physical building and commissioning follow. Neither the IEA nor the 2024 S&P observed timeline is an isolated stopwatch for regulatory review.

For the 127 operating mines S&P examined, the displayed mean stages are 11.9 years from discovery through studies, 1.5 for the decision stage and 2.3 for construction to first output. Their total is 15.7 years, so study-stage time represents 75.80% of that sum. Applying the same arithmetic separately across gold, copper, nickel and zinc shows how the reported splits differ. These fractions are ratios of category mean durations, not the average of individually observed project ratios. S&P 2024, average lead time by metal type.

Discovery and studies versus construction. Time shares of summed reported stages, not of a permit application.
Figure 4: Time shares of summed reported stages, not of a permit application. Sources: S&P Global Mine Development Times 2024, p. 16. See the full supporting table below.
View chart data

Time shares of summed reported stages, not of a permit application.

Discovery and studies versus construction
Operating groupDiscovery/studies (%)Construction (%)
Gold78.2913.82
Copper76.5414.81
Nickel62.8622.29
Zinc72.6114.01
All mines75.814.65

Figures retain the source units and definitions.

S&P Global Mine Development Times 2024, p. 16

Download chart data · Download chart SVG

Scroll the full table to compare columns and rows. The complete data are also available as a CSV.

Where the time went in operating mines
GroupMine countDiscovery through studies (years)Construction decision (years)Construction (years)Reported total (years)Sum of rounded stages (years)Discovery and studies (%)Decision (%)Construction (%)
Gold7011.91.22.115.215.2078.297.8913.82
Copper3412.41.42.416.216.2076.548.6414.81
Nickel1311.02.63.917.517.5062.8614.8622.29
Zinc911.42.12.215.815.7072.6113.3814.01
All mines12711.91.52.315.715.7075.809.5514.65

S&P Global Mine Development Times 2024, p. 16 · Download matching CSV

Derived shares use sum of displayed stage averages, not rounded published total. Named subgroup counts sum to 126; headline cohort is 127.

The zinc stage averages sum to 15.7 years while the printed total is 15.8. Rounded components should not be forced to reconcile by assigning the difference to an unreported phase. Similarly, the four named metal counts add to 126, but the all-mines cohort is reported as 127. We retain both source values instead of constructing an undocumented fifth category. These are important cautions when using weighted averages to reconstruct a headline mean.

What changes when unfinished projects enter a mine lead-time sample?

Completed-mine averages are conditional on a project having reached production. They can omit long-running projects still in evaluation, companies that stopped development, and resources which have not proved economic. The broader June 2024 S&P dataset includes 268 properties; 127 operating and 141 non-operating. The non-operating group therefore represents 52.61% of its expanded sample. This is a cross-sectional property count, not the probability a mine will open in any particular country.

Operating versus expanded cohort count
Project statusCountShare of expanded cohort (%)
Operating12747.39
Non-operating14152.61
Total268100.00

S&P Global Mine Development Times 2024, p. 19 · Download matching CSV

Count subtraction: 268 minus 127. Cross-sectional sample structure, not probability of opening.

The detailed table on page 20 shows a particularly useful comparison: ten of thirteen US properties were non-operating. In Australia it lists 18 non-operating and 11 operating; in Canada 19 and 11. The page 19 narrative instead gives Canada 29 and Australia 30 properties. Both are reproduced with their correct respective locators; component calculations here use the detailed table on page 20. We do not silently correct the publisher’s numbers or pretend the discrepancy is explained. Narrative sample and detailed status table.

Three-country detailed project cohort
CountryOperating projectsNon-operating projectsDetailed table totalNon-operating share (%)Operating avg. in-situ value (USD bn)Non-operating avg. in-situ value (USD bn)
Australia11182962.0733.422.2
Canada11193063.3314.748.2
United States3101376.9211.8103.9

S&P Global Mine Development Times 2024, p. 20 · Download matching CSV

Page 20 table. In-situ figures are source estimates, not realised revenue or valuation. Page 19 narrative reverses Canada and Australia total counts; do not merge.

The in-situ values reported with these status groups help explain why researchers cannot infer an opening rate from counts alone. These are estimates of resource material in the ground, not operating revenue, a company's market capitalisation, a discounted project valuation or evidence that capital can be raised at that amount. An operating property and an undeveloped resource may differ greatly in size, grade, infrastructure and economics. The observed and expanded sample averages answer different questions, and directly subtracting them does not measure permitting delay.

Which named US resource projects were already decades old in 2024?

S&P identifies specific examples of non-operating properties with substantial elapsed age. The examples below use their age at the 2024 report, rather than extrapolating to today or saying that the elapsed period is the time spent obtaining permits. The source table provides the US state and year of discovery; these are retained alongside each elapsed age. The report also discusses the reasons why extended development can arise; age alone cannot establish the reason for a specific property’s trajectory. S&P 2024 named project examples.

Selected non-operating US project ages in 2024
ProjectUS stateDiscovery yearElapsed age shown (years)
CopperwoodMichigan200816
MaturiMinnesota200618
ResolutionArizona199529
PebbleAlaska199034
Lithium NevadaNevada197846

S&P Global Mine Development Times 2024, p. 18 · Download matching CSV

Selected examples on publication date, not representative sample, current ages, eventual opening dates, or permitting-only durations.

If a researcher wants an actual historical time-to-production distribution, the required data are individual discovery and startup dates, a precisely defined entrant population and an observation cutoff, with unfinished observations marked as right-censored. A survival-analysis method can then distinguish the probability of reaching a milestone from the mean among completed properties. Projects that are abandoned present another outcome rather than a future opening that should simply be imputed. The aggregate figures cited here do not provide those underlying observations, so they cannot support a median, percentile distribution, failure probability or causal ranking of legal systems.

Which benchmark should be used for copper, nickel or lithium planning?

The IEA’s historical copper group averaged 16.8 years and the S&P copper operating group averaged 16.2 years. Their numerical proximity is useful context, but they are distinct source cohorts, not replicate observations from the same sample. For nickel the IEA separates sulfide and laterite operations, while S&P reports a broader nickel group. A single “critical mineral mine” mean can obscure major technology and deposit differences; an example involving a lithium brine and a deep hard-rock copper deposit is particularly poor as a direct comparison.

A good forecast or research brief should record the mineral and deposit type, project scale, brownfield versus greenfield status, start and end milestones, observation cutoff and whether estimates or completed dates are counted. Expansion at an operating site, construction of a new plant and bringing a discovery to first sale can each be legitimate projects, but their elapsed periods differ. Where the question is about permits specifically, obtain actual application, approval and appeal dates. Where it is about primary supply needed for an energy scenario, first production is not necessarily equivalent to the year full design capacity is achieved. See the copper supply forecast comparison for the separate mine-output requirement.

Methodology and sources

The expanded comparisons retain original source periods and row-level source references. Formulas, scope and precision are documented immediately beside each table, in the downloadable methods and source-cell ledger. Rounded primary values are not treated as exact unrounded observations.

The IEA figures come from its chart data for global lead-time stages and five mineral or geographic groups. The data are published under CC BY 4.0. AMR sums the three stage means and calculates the ratio of each stage to the sum. The nickel difference is laterite minus sulfide.

S&P Global Market Intelligence’s June 2024 Mine development times: The US in perspective was prepared for the National Mining Association. AMR transcribed the reported summaries from the executive summary, the observed samples and the expanded method. Cohort reweighting or project-level estimates would require project-level inputs and milestone definitions.

Glossary

  • Discovery-to-production: Elapsed time from discovery to first production under the study’s own milestone definitions.
  • Opening cohort: A group of mines grouped by when they began production.
  • Feasibility: A project study milestone. The IEA chart includes exploration through feasibility in the early stage.
  • Construction planning: A separate 1.8-year average stage in the IEA chart.
  • First production: The observed or estimated endpoint used by the study to stop the development clock.
  • Projected startup year: The estimated end date used for a mine or project yet to enter production.

Sources

Cite a specific finding

Copy the exact comparison with its period, scope and original evidence.

The three IEA stage means sum to 16.9 years

AMR sums the IEA’s published 12.5, 1.8 and 2.6-year stage averages to 16.9 years. The discovery-through-feasibility stage accounts for about 74% of that sum.

The IEA sample covers major mines that began production in 2010–2019.

American Mineral Registry. AMR sums the IEA’s published 12.5, 1.8 and 2.6-year stage averages to 16.9 years. The discovery-through-feasibility stage accounts for about 74% of that sum. The IEA sample covers major mines that began production in 2010–2019. https://americanmineralregistry.com/research/mine-development-lead-time-statistics#mine-lead-time-stage-sum Original evidence: https://www.iea.org/data-and-statistics/charts/global-average-lead-times-from-discovery-to-production-2010-2019
HTML attribution<a href="https://americanmineralregistry.com/research/mine-development-lead-time-statistics#mine-lead-time-stage-sum">American Mineral Registry</a>. AMR sums the IEA’s published 12.5, 1.8 and 2.6-year stage averages to 16.9 years. The discovery-through-feasibility stage accounts for about 74% of that sum. The IEA sample covers major mines that began production in 2010–2019. Original evidence: <a href="https://www.iea.org/data-and-statistics/charts/global-average-lead-times-from-discovery-to-production-2010-2019">IEA source</a>.

Supporting table · Permanent finding link · Matching CSV · IEA source

Laterite and sulfide nickel had different lead times

The IEA reports 19.5 years for laterite nickel and 12.8 for sulfide nickel, a 6.7-year difference calculated by AMR.

Observed mine opening cohorts in 2010–2019. The group averages describe selected mines.

American Mineral Registry. The IEA reports 19.5 years for laterite nickel and 12.8 for sulfide nickel, a 6.7-year difference calculated by AMR. Observed mine opening cohorts in 2010–2019. The group averages describe selected mines. https://americanmineralregistry.com/research/mine-development-lead-time-statistics#nickel-mine-lead-time-types Original evidence: https://www.iea.org/data-and-statistics/charts/average-observed-lead-times-from-discovery-to-production-for-selected-minerals-2010-2019
HTML attribution<a href="https://americanmineralregistry.com/research/mine-development-lead-time-statistics#nickel-mine-lead-time-types">American Mineral Registry</a>. The IEA reports 19.5 years for laterite nickel and 12.8 for sulfide nickel, a 6.7-year difference calculated by AMR. Observed mine opening cohorts in 2010–2019. The group averages describe selected mines. Original evidence: <a href="https://www.iea.org/data-and-statistics/charts/average-observed-lead-times-from-discovery-to-production-for-selected-minerals-2010-2019">IEA source</a>.

Supporting table · Permanent finding link · Matching CSV · IEA source

The U.S. benchmark changes when unfinished projects enter

S&P’s report gives about 13 years for three observed U.S. mine openings and almost 29 years in the expanded 13-property sample.

The expanded study uses projected startup dates for unfinished properties and assumes 2030 where none was available.

American Mineral Registry. S&P’s report gives about 13 years for three observed U.S. mine openings and almost 29 years in the expanded 13-property sample. The expanded study uses projected startup dates for unfinished properties and assumes 2030 where none was available. https://americanmineralregistry.com/research/mine-development-lead-time-statistics#us-mine-lead-time-cohorts Original evidence: https://cdn.ihsmarkit.com/www/pdf/0724/SPGlobal_NMA_DevelopmentTimesUSinPerspective_June_2024.pdf#page=17, https://cdn.ihsmarkit.com/www/pdf/0724/SPGlobal_NMA_DevelopmentTimesUSinPerspective_June_2024.pdf#page=19, https://cdn.ihsmarkit.com/www/pdf/0724/SPGlobal_NMA_DevelopmentTimesUSinPerspective_June_2024.pdf#page=6
HTML attribution<a href="https://americanmineralregistry.com/research/mine-development-lead-time-statistics#us-mine-lead-time-cohorts">American Mineral Registry</a>. S&amp;P’s report gives about 13 years for three observed U.S. mine openings and almost 29 years in the expanded 13-property sample. The expanded study uses projected startup dates for unfinished properties and assumes 2030 where none was available. Original evidence: <a href="https://cdn.ihsmarkit.com/www/pdf/0724/SPGlobal_NMA_DevelopmentTimesUSinPerspective_June_2024.pdf#page=17">S&amp;P Global report, p. 17</a> · <a href="https://cdn.ihsmarkit.com/www/pdf/0724/SPGlobal_NMA_DevelopmentTimesUSinPerspective_June_2024.pdf#page=19">S&amp;P Global report, p. 19</a> · <a href="https://cdn.ihsmarkit.com/www/pdf/0724/SPGlobal_NMA_DevelopmentTimesUSinPerspective_June_2024.pdf#page=6">S&amp;P Global report, p. 6</a>.

Supporting table · Permanent finding link · Matching CSV · S&P Global report, p. 17 · S&P Global report, p. 19 · S&P Global report, p. 6

Development time is concentrated before building starts

For S&P Global’s 127 operating mines, discovery through studies averaged 11.9 years, decisions 1.5 and construction 2.3. Discovery through studies therefore accounted for 75.80% of the sum of rounded stage means.

S&P 2024 sample; not permitting time or an estimate for an individual project.

American Mineral Registry. For S&P Global’s 127 operating mines, discovery through studies averaged 11.9 years, decisions 1.5 and construction 2.3. Discovery through studies therefore accounted for 75.80% of the sum of rounded stage means. S&P 2024 sample; not permitting time or an estimate for an individual project. https://americanmineralregistry.com/research/mine-development-lead-time-statistics#mine-development-before-construction Original evidence: https://cdn.ihsmarkit.com/www/pdf/0724/SPGlobal_NMA_DevelopmentTimesUSinPerspective_June_2024.pdf#page=16
HTML attribution<a href="https://americanmineralregistry.com/research/mine-development-lead-time-statistics#mine-development-before-construction">American Mineral Registry</a>. For S&amp;P Global’s 127 operating mines, discovery through studies averaged 11.9 years, decisions 1.5 and construction 2.3. Discovery through studies therefore accounted for 75.80% of the sum of rounded stage means. S&amp;P 2024 sample; not permitting time or an estimate for an individual project. Original evidence: <a href="https://cdn.ihsmarkit.com/www/pdf/0724/SPGlobal_NMA_DevelopmentTimesUSinPerspective_June_2024.pdf#page=16">S&amp;P Global Mine Development Times 2024, p. 16</a>.

Supporting table · Permanent finding link · Matching CSV · S&P Global Mine Development Times 2024, p. 16

The US detailed sample is predominantly non-operating

Ten of 13 US properties in S&P’s June 2024 detailed table were non-operating (76.92%). This was the sample composition, not a failure rate.

Source page 20; narrative and table disagree for Australia and Canada only.

American Mineral Registry. Ten of 13 US properties in S&P’s June 2024 detailed table were non-operating (76.92%). This was the sample composition, not a failure rate. Source page 20; narrative and table disagree for Australia and Canada only. https://americanmineralregistry.com/research/mine-development-lead-time-statistics#us-mines-expanded-sample-share Original evidence: https://cdn.ihsmarkit.com/www/pdf/0724/SPGlobal_NMA_DevelopmentTimesUSinPerspective_June_2024.pdf#page=20
HTML attribution<a href="https://americanmineralregistry.com/research/mine-development-lead-time-statistics#us-mines-expanded-sample-share">American Mineral Registry</a>. Ten of 13 US properties in S&amp;P’s June 2024 detailed table were non-operating (76.92%). This was the sample composition, not a failure rate. Source page 20; narrative and table disagree for Australia and Canada only. Original evidence: <a href="https://cdn.ihsmarkit.com/www/pdf/0724/SPGlobal_NMA_DevelopmentTimesUSinPerspective_June_2024.pdf#page=20">S&amp;P Global Mine Development Times 2024, p. 20</a>.

Supporting table · Permanent finding link · Matching CSV · S&P Global Mine Development Times 2024, p. 20

Data and downloads

No account or form is required. CSV tables preserve the article’s units, evidence periods and source estimates.

Iea lead time stages (CSV)

Iea mineral lead times (CSV)

Lead time benchmarks (CSV)

Sp cohort comparison (CSV)

Sp observed lead times (CSV)

Expanded research datasets

Where the time went in operating mines (CSV)

Three-country detailed project cohort (CSV)

Selected non-operating US project ages in 2024 (CSV)

Operating versus expanded cohort count (CSV)

Cite this page

Retain the original producer, observation or projection year, and scope when citing any figure.

American Mineral Registry. "Mine Development Lead Times: Discovery to First Production." American Mineral Registry, November 2026. https://americanmineralregistry.com/research/mine-development-lead-time-statistics/